Balfour Beatty's delayed sea defence project at Sea Palling was
again on hold this week as bad weather dashed the contractor's
hopes of making up lost time.
The offshore site has been at a standstill since 13 April when a
vital 3,600 tonne crane barge was damaged after breaking loose in
heavy seas.
Work briefly recommenced on Sunday (15 May), but on Monday night,
as Force 6 winds raised the waves to a height of 2.5m, work was
again called off. The œ6 million scheme to build four
protective reefs off the Norfolk coast was still on hold as CJ went
to press on Tuesday.
The contractor hopes to speed up construction by introducing two
self-propelled side-discharging barges which could deliver rock to
the reefs without the help of the crane. These would enable work to
proceed on two reefs at once, giving the project a chance of
completing on schedule in September.
But with the new equipment also unable to operate until calmer
conditions return, Balfour Beatty now faces an even grimmer
struggle to finish the contract on time and before the winter makes
further progress unlikely.
The project has suffered a series of disasters since its start in
April last year. Two people have been killed while working on the
scheme, and equipment has broken loose and drifted ashore four
times.