A radical restructure of the Joint Contracts Tribunal limiting the
powers of veto is being sought by contractor members of the
Construction Industry Employers Council. It wants the JCT to be
split into four separate 'colleges' which would represent clients,
consultants, main contractors, and subcontractors. Only the
'college' representing the parties to a particular contract form
would be entitled to vote on its terms.
In a weighty, and at times controversial, statement of evidence to
the Latham inquiry, CIEC contractors argue strongly that
pay-when-paid terms must remain a freely available option. They
support a move to milestone payments and want payment of
subcontractors within 30 days to be written into all standard
forms. In addition, they back accreditation of contractors and the
use of adjudication to resolve disputes.
The CIEC submission was compiled by the BEC, FCEC, and FMB.
Separate evidence has been forwarded to Latham by specialist
subcontractor and building materials producer members of the
council.
Key features of the contractors' evidence include -
l Contracts Tribunal: the new 'college' structure should enable the
JCT to publish a full range of documents including domestic forms
of subcontract and conditions of engagement between client and
consultant. This would lead to the availability of 'a matrix of
contracts which are fully compatible with each other.'
l Payment: despite support for pay-when-paid, a compromise is
offered. Where pay is delayed by the client due to the default of
the main contractor or another subcontractor, then the main
contractor should pay 'innocent' subcontractors. And subcontractors
appointed on a genuinely domestic basis should retain the right to
be paid in full in the event of client insolvency.
To increase contractors' security of payment, a trust should be
imposed by statute on the approximate value of three months' work.
Clients should honour architect's certificates within seven rather
than 14 days.
The introduction of a contractor's lien is not supported. The QS or
engineer should be contractually obliged to measure and value
variations within a fixed timescale. Where this is not done, the
client should be required to pay interest. And final accounts
should be settled within three months of completion with interest
again paid in the event of failure.
l Qualification: it is acknowledged that a system of accreditation
of contractors for public sector work 'is becoming desirable.' But
companies should not be forced to adopt quality systems such as
BS5750 to become accredited.
Adjudication: it is argued that adjudication should be introduced
into all JCT main contract forms, except for the minor works form
or any form involving a consumer.
l Government: the DoE should have a co-ordinating and advisory role
among all Government departments setting an example of best
practice.
l Bonds: the sum bonded should not exceed 10% of contract value and
the liability under bond should terminate on practical completion.
Government is strongly urged to condemn any form of on-demand
bond.
l Implementation: CIEC opposes the idea of a regulatory board to
implement any recommendations in the final Latham report. It calls
for the team of inquiry assessors to continue for a further six
months to carry forward the proposals before considering any such
board.
Commenting on the CIEC submission this week, Jennie Price, legal
affairs director at the BEC, said: 'The whole exercise has
generated a new spirit of communication. We have talked to more
bodies more openly than we have for a long time.'