Allegations in last week's Daily Mirror that the new DSS HQ, in
Leeds is a 'fire trap' have been vigorously denied by the client
and contractor. The œ55 million D&B showpiece, Quarry
House, was built for the DSS and DoH under a fast-track programme
by main contractor Norwest Holst with Amec as project
manager.
The fire trap allegations came from subcontractor Chris Richardson,
who claims that parts of the building's fire protection system are
seriously deficient. Richardson was brought in by Norwest Holst to
provide partitioning labour and undertake remedial work on 820 of
the building's 1,420 fire dampers - electronically operated metal
shutters usually housed in ducts.
Richardson was fired two weeks ago following complaints from his
workmen that they had not been paid. He claims that 90% of the 300
fire dampers he had looked at were useless and that fire breaks and
partitions were missing. He also claims he was told to work between
7pm and 6am so as to keep his work strictly confidential. There
were also separate allegations that the fire alarm and sprinkler
system was faulty.
The DSS and Norwest Holst concede there are problems with some of
the fire dampers, but say these are installation problems and that
all 1,420 dampers are operational. They say the fault arose from
lack of co-ordination between damper and partition installation.
Both emphatically deny that there are any problems with the fire
alarm and sprinkler system or that there is any risk to staff.
The DSS has issued a statement saying: 'The work has necessarily
been undertaken outside normal working hours to minimise
inconvenience to staff. At no time has the need for this work put
the personal safety of staff working in the building at risk. The
building has regularly and independently been inspected by fire
precaution specialists as each phase has been completed.'
Norwest Holst is still operating under its 12-month guarantee and
is preparing the building for a fire certificate application. A
spokeswoman said: 'There are no fire breaks or fire partition walls
missing. All are of the correct guide/standard. The work being
carried out is at the junction of the wall and wall damper.'
The problems with the fire dampers were picked up by Norwest Holst
itself. The contractor brought the problem to the client's
attention and engaged WS Atkins to provide remedial work proposals.
A WS Atkins spokesman says: 'We were engaged to provide advice and
were paid a fee. In fact our advice was not then taken by the
contractor.'
Norwest Holst says the WS Atkins proposals were 'subsequently
amended after discussions with the fire officer, damper
manufacturer and partition manufacturer.' It says that 50% of the
820 dampers have been rectified and the rest are being seen to.