few weeks ago John Laing workers uncovered 30 skeletons at
Stratford, east London, during construction of a train depot for
the Jubilee Line Extension. In this instance the medieval bones
will not hold up construction work, but that is not always the
case.
Discovering unexpected archaeological remains can almost be as much
of a problem as unforeseen ground conditions for contractors.
Tunnel-boring machines can get clogged up with ancient timbers; 6ft
walls can suddenly be encountered 20ft underground. Throughout the
British Isles, all manner of ancient artefacts lie in wait for the
unsuspecting contractor.
For archaeologists it has been frustrating to see so much material
disappear under concrete and brick. But the profile of archaeology
has risen along with other environmental concerns in the last few
years. The Government is trying to establish a balance between the
need to preserve the country's heritage and the need to develop.
The main vehicle for this is PPG16 Archaeology and Planning
introduced in November 1990. This gives all ancient remains a
measure of protection, if only temporarily. If archaeological
remains are found on site, work has to stop while the remains are
inspected and their worth evaluated.
To try to avoid last-minute discoveries, PPG16 advises developers
to undertake an archaeological evaluation of any potential site,
before applying for planning permission. PPG16 also insists that if
developments do go ahead on sites with archaeological remains, then
as much of the remains as possible must be preserved in situ.
The changes in the planning guidance have led to an explosion of
archaeological activity. Archaeologists are now regularly taken on
by developers, mineral extractors and contractors as consultants to
assess the potential archaeological importance of work sites. Both
archaeologists and contractors agree that relationships have
greatly improved since 1990.
However, the changes have not solved all the old conflicts and
have, perhaps inevitably, brought some new problems with them.
Maurice Webb, director of industry and environmental affairs at the
FCEC, says: 'We find that the greatest problem is where local
authorities get involved and don't have the resources to do the job
quickly. Then the work drags on and you get delays. The
contractor's programme slips and he can incur heavy
penalties.'
The problem, according to Webb, is that in a lot of cases there is
no specific timetable for archaeological research once material is
turned up on site. The FCEC is making representations to the DoT
and DoE to try to establish a timescale for archaeological
research.
Mineral extractors can also find themselves running into
difficulties on occasions. Steven Fidgett of the Sand And Gravel
Association's planning executive says: 'Archaeology is an issue
that is increasing in its impact and importance. We have a lot of
sympathy with it as an environmental concern, but inevitably it can
lead to conflict.'
One problem is that local authorities sometimes demand quite
extensive archaeological investigation before considering other
issues in the planning application. 'There is no point spending all
that money on an archaeological investigation, if the planning
application is then turned down later for other reasons.
Investigations should be done after all the other planning
considerations have been passed,' says Fidgett.
The other worry is that when a planning application is favourably
considered, but has an archaeological constraint placed on it,
operators can sometimes feel they have signed a blank cheque. 'In
most cases the archaeological work is quite acceptable, but on
occasions digs can run on and on and cost hundreds of thousands of
pounds. And the finds may only be of local or regional importance,'
says Fidgett.
Operators can certainly get their fingers burnt if they are not
clear about the archaeological risks before purchase. One mineral
company bought the mineral rights to an area, but signed a document
agreeing to preserve any archaeological remains. Remains were found
in part of the site in a very good state of preservation, buried
beneath alluvium. It turned out that the cost of excavating and
preserving the remains was more than the value of the gravel to be
extracted. The company abandoned that part of the site.
But if archaeologists sometimes frustrate contractors, the converse
is also true. It is not unknown for contractors to remain
discreetly silent when it suits them.
In the mid-1960s a new development uncovered the missing west wall
of Roman Lincoln. The story was splashed on the front page of the
local newspaper. A certain retired contractor was not in the least
bit surprised. He had found the wall in the gardens of Victoria
Terrace back in the 1930s while laying gas mains. But instead of
reporting the major find, he just bent the pipes over the wall and
covered it up again. The suspicion remains that contractors tend to
do much the same thing today.
Another problem for archaeologists is when they have only a
watching brief for a site.
John Oxley, principal archaeologist at York City Council, says:
'When you have a watching brief there is a great potential for
conflict, if the archaeologist's brief is not set out in the
contractor's contract with the client. Details of access and times
can only really be resolved by the individuals on site.
'It may be down to a foreman to agree, or not, to move his men off
a certain area and let the archaeologist record what has been
found. On a full excavation you usually have a much clearer
contractual relationship,' says Oxley.
George Lambrick, deputy director of Oxford Archaeological Unit,
says: 'On watching briefs the detailed working practices need to be
worked out and understood. The objectives and methods of
contractors and archaeologists are so different. It helps
enormously if you have very clear agreement about access and can
make the most of any flexibility in the contractor's
programme.'
Public concern over the need to preserve archaeology has risen in
the last few years, along with environmental issues generally. In
1988 there was a public outcry in York when a new development on
the site of the former Queen's Hotel destroyed important
archaeological remains.
York City Council realised it had to reconcile the need for
development and the need to preserve archaeological remains. So the
council and English Heritage commissioned Ove Arup to find a
solution. Arup came back with a set of proposals which said it was
possible to build any type of building in York, given the
prevailing ground conditions and height restrictions
(five-storeys), and still preserve 95% of the archaeology in
situ.
The solution was to use regularly spaced case bored piles, which
could core or chisel through remains. The council accepted the
proposals and incorporated them into the local draft plan.
PPG16 and York-style compromises have helped to reduce the conflict
between the need to develop and the need to preserve.
Archaeologists are relieved that more of our ancient heritage is
being preserved.
'Things have improved dramatically since 1990,' says Andrew Lawson,
director of Wessex Archaeology. 'Before then it wasn't clear how
archaeology should be regarded and there was mistrust and conflict,
but now PPG16 makes it very clear that archaeology must be taken
into account.'
Builders now have much clearer guidelines and can plan ahead
accordingly. Richard Morris, director of the Council for British
Archaeology, says: 'The key to effective success and good relations
between contractors and archaeologists is good long term planning.
Archaeology is slow, painstaking and labour intensive. The further
ahead of the construction work you can plan for excavation, the
better. Of course, you will always get circumstances where that
can't or doesn't happen.'
In some cases development has been allowed to go ahead with the
proviso that the remains are not only preserved, but remain
visible. The most celebrated example of this is the new building
planned for London's Guildhall Yard East. Here, the building's
design had to be changed to incorporate part of the remains of the
Roman amphitheatre within the foundations of the new building.
Visitors will be able to view the remains from a gantry
above.
More often, development goes ahead after delay to allow a rescue
dig to be done before construction begins. This is happening at No
1 Poultry in the City of London. Planning permission was granted
before the advent of PPG16 and only a watching brief was required.
However, the developers, Altstadtbau, have agreed to contribute
œ2 million towards the cost of excavation, which will last
nearly a year.
The main contractor, Laing, will put in the foundation slab and
work above it, while the archaeologists work beneath it, using the
holes made for the lift shafts to extract the spoil. Once the dig
is finished, Laing will put the cellars in.
œ2 million is a considerable sum and indicates the scale of
the costs involved on a major excavation. BACMI released a
three-year study in March this year, which examined the cost of
archaeology to the industry between 1991 and 1993. The total was
over œ10 million.
The cost of funding pre-application archaeological evaluations and
of funding post-permission surveys and rescue digs amounted to
œ2.2 million. The cost of delays caused by rescue digs was
around œ110,000, and the cost in terms of lost aggregate sales
of mineral sterilised because of the need to safeguard
archaeological remains amounted to œ8.4 million.
Roads Minister Robert Key was heard lamenting the increased cost of
archaeology to the DoT earlier this year. The Department's costs
have risen from œ329,000 in 1989-90 to œ2.2 million last
year, possibly reaching œ3 million this year. However, as
archaeologists pointed out to Key during a seminar on the subject
in May, the rise in costs is a direct result of the Government's
own polluter pays policy. Before the introduction of polluter pays,
the DoT had usually managed to get someone else to pay for the
work.
But there is a genuine concern on both sides of the fence to get
value for money. Naturally, not everyone agrees on what value
means. CBA director Richard Morris wants the money spent on digs,
which are likely to enrich the public and advance human knowledge.
'I'm worried that patronage has partly switched from the state to
the developer, whose agendas are very different. Things could get
slapdash with cheap jobs and be archaeologically uninteresting.
It's not just another planning hoop to be jumped through,' says
Morris.
For their part, mineral operators and contractors are concerned at
the restrictions imposed by some of the current legislation. Ian
Cromie, assistant planning officer at BACMI, says: 'Sometimes the
planning restrictions are overprotective and we are spending money
on material that does not merit preservation.'
Archaeologists do not necessarily disagree with this. Many would
prefer funds to be spent on truly important sites rather than
spread over a wider area. John Oxley says: 'There has been a lot
done in archaeology over the last 20 years. It's time to take
stock. We need to figure out what we want to know and then pick our
sites carefully.' Music to the industry's ears perhaps? The boom in
archaeology since the introduction of PPG16 in 1990 has led to
considerable commercial success for some archaeological
contractors. Some now have turnovers of up to œ1 million and
bid for contracts like any other consultant or contractor. Two of
the biggest names are Wessex Archaeology based in Salisbury and
Oxford Archaeological Unit.
Wessex Archaeology is a registered charity, which is undertaking
170 projects in 1993-94, a rise of 36% on 1992-93 and 50% up on the
year before. About a third of these are evaluations of sites to
assess their archaeological potential, of which about half are desk
top studies. About 75 of the jobs are advance works. Only ten of
the 170 jobs are full scale excavations. Director Andrew Lawson
says the average cost of an assessment is about œ1,500 and
œ5,500 for an evaluation.
Oxford Archaeological Unit was founded 21 years ago, originally
concentrating on work in the Oxford area. It started to expand in
1976 and now works over most of Britain and occasionally abroad.
Deputy director George Lambrick says: 'We work on a wide variety of
projects covering monuments, historic buildings and landscapes. We
do a lot of work on road schemes carrying out specialist studies
for environmental assessments. We advise developers, contractors
and mineral operators on the implications of what their
developments might be.'