Essentially what Tommy Melling says is correct. His contract went
up from œ42,000 to œ72,000 and we have paid all except
œ5,000. That means we have paid œ25,000 more, but we have
actually only received so far an extra œ11,000 against this
work from McAlpine. In all they still owe us around œ180,000
and, of course, we will pay up when we receive some more money. It
is all under discussion still and we have got to check who is owed
what.
In general we would like to see the end of the 'pay when paid'
clause in contracts - that would help. Hawkins Structures did not
carry out weekend working on McAlpine's instructions and this is a
matter between them and their subcontractor.
Bluebell Architecture have been paid for the work they carried out.
Any reduction in their valuation was as a result of invoicing in
advance of carrying out the works. In the event they failed to
complete the works and McAlpine has had to carry out substantial
works directly in order to achieve completion. I have run my own
steel erecting business for 30 years and have never known the
market to be as bad as it is now. Here is an example of how things
go wrong on site in contractual relations today.
There is a problem on site, our foreman rings the client and all we
get is 'he's not in' or 'he's in a meeting.' If you do manage to
reach the person you want, they say they'll look into it or that
they can see the problem and can we put it right. Yes, we say, we
can, but what about payment? Don't worry you will get paid, we are
told. This is the joke of the century. If you believe it, you will
end up out of pocket. I believe trusting assurances like these has
cost me œ17,695.
My tale of woe starts in September 1993, when I tendered for three
contracts:
1. Student Village, Manchester - 950t for Royden Engineering of
Rainford - (œ35,000).
2. Marks & Spencer, Warrington - 670t for Hawkins Structures of
Scarborough (œ42,000).
3. Morrisons Supermarket, Warrington - 320t for Billington
Structures, Wombwell (œ19,000).
I was awarded all three contracts but was confident I could make
them pay even though they were low prices.
However, through late information from architects resulting in late
deliveries of steel, things were not going well on all three
contracts. I was always told I would be paid extra to contract sums
for additional work. Where possible I had time signed for, but at
other times when things went wrong I could not obtain a signed time
sheet but was always told "don't worry you will be paid"!
This is the subbie's dilemma. Do you wait for the formal go-ahead
while costs are mounting for every minute's delay, or do you get on
with the work and hope that you are paid properly come the
reckoning day?
On the Student Village project in Manchester for Royden Engineering
my problems began when I went to the office to collect money and
discuss final account for extras to the contract. I calculated that
the balance owed was œ9,211.44, but was told I would be paid
œ5,014.20. There was no discussion, and although I at first
refused to accept it in the end I had to agree.
On the Marks & Spencer project in Warrington for Hawkins
Structures my contract grew from œ42,000 to œ72,000 due
to weekend working and extra to contract work. All my time was
signed for on daywork sheets by their own site agent. I had a
shortfall on this contract of œ5,000. I was and am still being
told that the main contractor, Alfred McAlpine, are holding
œ200,000 back from Hawkins so they are not paying any money
out until they are paid.
The Morrison Supermarket job in Warrington was for Billington
Structures and now I will not work for them again. We waited from
March until July for answers as to why they were not paying certain
invoices which are based on claims that I say have been signed for.
On three contracts I have erected for this company there is money
outstanding totalling œ2,094.51.
On the Marks and Spencer project I took on another contract for a
company called Bluebell Architectural who were on site when the
main steel was being erected. They approached me and asked if I
would price for the erection of the canopy steelwork. I quoted
œ4,700 which was accepted and again this contract grew to
œ6,403.33 through extras to contract. McAlpine again did not
pay, slashing their end of month valuation by œ50,000. Hence
Bluebell could not pay me. Unless Bluebell is paid I have very
little chance of receiving my money.
The total of my losses mentioned above is œ17,695.
In my opinion the cause of all these problems is:
1. Late information from the architects, resulting in late
deliveries of steel and fabrication errors due to drawings not
being checked, which is due to understaffing.
2. Management contracts where a number of weeks is allowed for the
contract which is called fast-track. There is no allowance for
things going wrong. I do not think any contractors on the Marks
& Spencer contract made any money and all the ones I spoke to
could not wait to finish this particular contract and never again
would they work on a management contract site.
The big guns demand progress but won't come through with the money.
The small firms at the end of the chain suffer like myself. I will
survive as I have put personal money in the firm to keep it afloat.
Steel fabricators take on too much work and then have to sublet it
to other fabricators. If steel is not fabricated 'in house,' there
is no control over deliveries, ie steel is delivered late or not at
all. Royden paid all Mr Melling's contract work before the due date
and in most cases between 30 and 45 days against the contracted 60
days. Retention of 5% was 'never' deducted.
Mr Melling was advised by Royden to compile a claim for any extra
and this would be pursued with the client and paid on a pay when
and if paid basis. The claim was never submitted.
We made a final offer which was, after some discussion, accepted,
of œ5891.69 for the outstanding balance.
Mr Melling signed for the cheque on a standard form which stated
'we accept this cheque for the value of œ5891.69 on behalf of
TH Melling as full and final settlement for work carried out at:
Student Village Manchester'. Royden does not accept that threats
were made at this juncture.
The meeting broke up amicably with Mr Melling requesting further
work and until last week Mr Melling was still being asked to submit
prices by our Sales/Estimating Department. Melling Services started
out with a œ19,000 contract. Tommy Melling can himself confirm
that he has received œ26,800 less retentions from us. I think
you have to read between the lines here. I don't know anyone who
gets fully paid for dayworks - signed or otherwise. And Tommy
Melling doesn't seem to understand that. He expects everything he
puts in just to be paid. We have dealt very fairly with his company
and I think he was being a little naive.