Less could mean more for House of Fraser's flagship London
department store Dickins & Jones. Less floor space that is, as
Plumb Interiors Contracting has removed a 7.2m diameter 'core' from
the centre of the four-storey Regent Street building, from which it
is now creating an atrium-like well. This feature, culminating in a
fibrous plasterwork dome with bronze grilles and hidden uplighting,
will vastly improve the store's internal appearance, opening up the
building from basement to roof level.
Plumb, a subsidiary of Hall & Tawse, has worked on more than 20
House of Fraser stores in the last decade, yet this œ3 million
refurbishment contract, covering shopfitting and M&E works, is
its largest and possibly most challenging. The client specified
that the store remain open throughout the entire 20-week works
programme, so the Plumb team completely sealed the central core
area behind a cleanly painted and inconspicuous hoarding.
Plumb liaises closely with House of Fraser to minimise disruption
to customers and ensure the efficient operation of the store,
explains Hall & Tawse group marketing director Mike
Smith.
Most of the noisier work, such as the demolition, has taken place
at night, he adds, 'and the public don't even know we're here'.
Store staff move merchandise to newly re-fitted sections as quickly
as the contractor begins work on the just-vacated areas, often in a
matter of a few hours, with both sides working around the clock.
'It's a real partnership between us and the client,' says Smith,
'and we have to be totally flexible'.
Plumb's first major task was to remove the six lifts and their
shafts, which previously occupied the central core area. This
involved the removal of 'very substantial' steelwork, says project
manager Len Ashley, including 9m-long universal beams, in addition
to 1.5t lift motors from the rooftop motor room. 'Our greatest
problem, though, is one of logistics, as we have no space to work
in and no access whatsoever.'
Its solution was a 2.5m-high 'tunnel' suspended from the ceiling of
the first floor and running from the central work area to the
store's Argyll Street exit. Sections of old steelwork, timber and
masonry were subsequently removed via the tunnel, and new materials
taken in.
The tunnel was located above the heads of shoppers, and House of
Fraser used the soffits on either side of the tunnel for display
purposes.
After clearing the old lift motor room, Plumb installed the dome
and then took out 15m x 17m rectangular sections from each of the
six floors above the lower basement level. It has constructed the
circular holes within these voids using steel rings brought into
the building in four sections.
Finishing work, now underway, includes laying marble flooring
around the well and fitting ornate bronze ballustrades.
A sophisticated ventilation system, with circumferential fire
shutters around the top two floor voids and fire curtains on lower
levels, is also in place. In the case of fire this will help create
a 'chimney effect', forcing smoke up through the grilles around the
dome, and out of the building.
Plumb is now putting in two new escalators having removed two
existing ones through a third floor window in addition to
installing two lifts in another part of the store.
The refurbishment, from the structure elements down to the Art
Deco-style furniture and fittings, were all designed by US-based
consultant HTI. 'They came up with the concept for the well,' says
Smith, 'but Plumb has made it work'.