Leading contractors are shunning alternative disputes resolution
(ADR) as a solution to site conflict despite its success in more
than 200 construction cases.
Although many of the big contractors such as AMEC, Balfour Beatty,
Sir Robert McAlpine and Trafalgar House are founder members of the
Centre for Disputes Resolution (CEDR) they make little use of the
system.
Stuart Sinclair of CEDR claims Balfour Beatty has spent 'a colossal
amount of money' on a dispute in the High Court with Ossery Road
(Skelmersdale) when mediation could have helped.
Sinclair said: 'It is disappointing. Some members don't refer any
cases to us. I hoped this case might first have been subjected to
mediation.'
Sinclair reckons that if contractors made fuller use of ADR the
industry's legal bill could be cut by a quarter - a saving of
œ100 million.
Since ADR, a cheaper alternative to conventional litigation,
arrived in the UK four years ago some 200 construction disputes
with a total value of œ385 million have been settled speedily
by mediation, the most popular form of ADR.
One of the biggest disputes to be settled in this way, involving a
œ7.5 million construction claim, was resolved in just five
days. The md of the firm of contractors involved said that if he
could have persuaded the client to switch to ADR two-and-a-half
years earlier, then each side would have saved œ1.5 million in
legal costs.
And this case is set to be dwarfed by a œ20 million
construction dispute that will be heard by ADR mediators
shortly.
However Sinclair is worried that ADR might be about to miss the
boat, the Latham report having arrived before contractors are
willing to stand up and fight for it to be included in the proposed
modifications to standard forms of contract.
'It is disappointing that Latham wasn't more positive about
mediation,' said Sinclair. 'His concept of having adjudication
during the contract, but before practical completion, is fine, but
after a contract is finished there should be a stage in the
resolution of disputes between the failure of negotiations and the
commencement of arbitration or litigation.
'At the CEDR, over 90% of all mediations are settled, so it must be
worthwhile,' he added.
'Ideally, the UK construction industry would have been further down
the ADR learning curve before Latham looked at the industry.
However, we can't afford to miss this opportunity to get mediation
clauses introduced. The IChemE contract has this clause - it is a
very sensible provision.
'The CEDR must lobby Sir Michael's forum as contractors themselves
are not yet fully persuaded to stand up and support ADR vocally in
public,' he said.