The Court of Appeal has answered two important questions about
clause 30.9 of the JCT Standard Form of Building Contract, 1980
edition, in its judgments in Crown Estate Commissioners v John
Mowlem & Co Ltd (1994), unreported, allowing an appeal against
a decision of Judge James Fox-Andrews QC, who was faced with
conflicting case law.
The questions, which are of general importance, are:
lDoes the court have power under section 27 of the Arbitration Act
1950 to extend time under clause 30.9.3 which, as amended, relates
to the effect of the final certificate in relation to arbitration
proceedings which have not been commenced within 28 days of its
issue? Judge Fox Andrews had answered that question in the
affirmative.
lOn the proper interpretation of clause 30.9.1.1, in the absence of
arbitration proceedings being commenced before or within 28 days of
its issue, is the final certificate conclusive evidence that only
those materials and workmanship that are expressly required to be
of a standard and quality which reasonably satisfies the architect
are to that quality and standard, as Judge Fox-Andrews, also
held.
In doing so, he followed the views expressed by the late Judge John
Newey QC in Darlington Borough Council v Wiltshier Northern Ltd
(1993) 37 Con LR 29 who, in dealing with a JCT 63 contract, ruled
that Clause 30(7) applied only to materials and workmanship
expressly stipulated to be to the architect's satisfaction who had
distinguished the earlier decision of Judge Thayne Forbes QC in
Colbart Ltd v H Kumar (1992) 28 Con LR 58 who was considering a
final certificate under IFC 84.
The latter decision was subjected to stringent criticism by
Professor Duncan Wallace QC, and by other commentators, because it
held that finality is not restricted to materials and workmanship
which are expressly reserved by the contract to the opinion of the
architect for approval of quality of standards, but includes all
materials and workmanship 'where approval of such matters is
inherently something for the opinion of the architect'.
The case attracted wide attention in the building industry because
of its implications for contractors for whom Judge Newey's decision
was welcome.
Unfortunately, the Court of Appeal prefers the wider view although
there is no doubt in practice a clear distinction between setting
contractual standards and ensuring compliance with them, and I do
not find their Lordships' reasons at all convincing. Lord Justice
Stuart-Smith dismissed Mowlem's Counsel's argument that both
Clauses 2.1.4 and 30.9.1.1 are concerned with fixing standards and
not with ensuring compliance with them, on the basis that the words
'where and to the extent that' in Clause 2.1.4. show that there
must be something to which the provision does not apply.
Here is the Lord Justice's reason: 'If the contract was tailor-made
for this project, there would be much force in this argument. But
is is not; it is a standard form of contract, no doubt drafted in
committee, and designed to cover a multitude of cases. In most, if
not all, cases they may well be superfluous but are put in out of
an abundance of caution.'
None of the members of the Court of Appeal accepted the submission
that Colbart was wrongly decided and all of them thought that the
wider interpretation was to be preferred. 'It would be strange that
the contract should specify an objective standard of reasonableness
only for the setting of standards for materials and workmanship and
not the far more important question of compliance,' said Lord
Justice Stuart-Smith. Anyone familiar with the labyrinthine
workings of the JCT would not think it strange at all!
As to the first question, the Court was also of the view that there
is no power to extend time under clause 30.9.3 and the message to
contractors is that if one wishes to raise a challenge, the notice
of arbitration must be served either before or within 28 days of
the issue of the Final Certificate. In fact, it is my unhesitating
view that the whole of clause 30.9 should be scrapped and the final
certificate should merely have a financial effect.
At present, clause 30.9.1 makes a general provision, subject to the
exceptions in clauses 30.9.2 and 30.9.3, that in any proceedings
arising out of or in connection with the contract, the final
certificate is conclusive evidence of everyone of the specified
matters. Where the final certificate thus becomes conclusive
evidence, the effect is that any claim in arbitration which seeks
to support some provision of the final certificate is bound to
succeed, and any claim that seeks to challenge a provision of the
final certificate is bound to fail, without any hearing on the
merits.
The 28-day time limit is very short and clearly Judge Fox-Andrews
felt that this was the sort of case where a discretion in the Court
to extend the time limit, where undue hardship is shown, would be
appropriate. But there is authority against this view, namely the
shipping case of Babanaft International Co SA v Avant Petroleum Inc
(1982) 1 WLR 871 which decided that a claim did not come within
section 27 of the 1950 Act where there was no clause in the
contract relating to arbitration which specifically provided that
claims should be barred unless notice to appoint an arbitrator is
given within the time fixed by the agreement. Clause 30.9 does not
do that and so there is nothing to extend.
In that case, the notice period was 90 days - which was more
generous than JCT 80's 28 days. But relying on Babanaft, the Court
held that Mowlem was out of time because of the clause 30.9.3
provision that, if the 28-day time limit is not met, an evidential
provision will apply and prevent any hearing on the merits.
So there we have it and the fault appears to be that of the
draftsman. There is no linkage in JCT 80 between clause 30.9, in
which the time bar is found, and the arbitration clause itself.