The controversial New Austrian Tunnelling Method has restarted on
the Jubilee Line Extension and could get underway again on the
troubled Heathrow Express project next month.
The Health and Safety Executive has given the Jubilee Line
Extension Project team the green light to use the method less than
three months after a NATM tunnel - being built by Balfour Beatty -
collapsed at the Heathrow Express.
But the HSE's all clear excludes complex junctions and larger
diameter tunnels - the JLE must still submit plans for these areas.
And the HSE is still concerned about the use of compensation
grouting - which strengthens the ground near the tunnels - and has
also asked for more information before this technique is
resumed.
JLE project director Hugh Doherty confirmed that NATM was
restarting on the two affected contracts - contract 102 (Balfour
Beatty-Amec) and Contract 104 (Costain-Taylor Woodrow) - and played
down concern about compensation grouting.
'We have not used compensation grouting in the 1km of NATM
tunnelling completed so far, though in some of the rest we are
making preparations in case we do need it,' he said.
Doherty's team also needs to satisfy the HSE over JLE's emergency
arrangements in the event of a collapse and to look at its liaison
with public utilities in the event of an emergency, particularly
the co-ordination with British Gas.
The HSE go-ahead gives contractors two to three months work,
provided work keeps clear of areas that need compensation grouting.
Doherty said that he expected any delays to be made up in the
overall Jubilee programme.
At Heathrow Express, investigators say they are 80% of the way
towards establishing the cause of the tunnel collapse on 21 October
1994.
Design teams are working on ways of opening up the problem area
next month - all options involve excavating the area affected by
the collapse but the project teams say that the preferred solution
could well involve NATM.
'We're confident of being back on the site of the collapse in
February,' said a spokeswoman for Heathrow Express. 'We are now
working to hold the original schedule which involves us completing
the project by December 1997.'
But the HSE's investigation at Heathrow is far from over. 'It is
months from being complete,' said a spokesman. 'We are still asking
Balfour Beatty for information.'
n Problems with a 5000t caisson at Durand's Wharf on Jubilee Line
Contract 107 have been resolved according to JLE. Dewatering was
not working, so the caisson was sunk to the bottom by compressed
air instead. Tunnelling, which was delayed, will get under way
later this month.