The widening of the M25 seems to go on forever, but in the process
it is making widespread use of some of the most up-to-date
construction systems, designed to lower costs and reduce the
environmental impact.
The 8.5km stretch between the M3 and the A3 now under construction
by Mowlem Civil Engineering not only incorporates one of the most
elaborate noise barrier systems so far installed in the UK, it also
makes greater use of reinforced soil structures than in any
previous project.
The carriageway is being widened on each side by converting the
existing hard shoulder into a traffic lane and constructing a new
hard shoulder alongside. To create the space required without
extending beyond the present fence line, particularly between
junctions 10 and 11, the contractors have had to cut into the
existing slopes in some places and build up the embankments in
others.
The much steeper slopes would normally be retained using
conventional means such as concrete retaining walls, sheet piling,
etc, and in fact the original design by the Department of Transport
proposed sheet piling and gabions for the support structures. The
suggestion that reinforced soil could be used as an alternative
came from Mowlem, using an in-house design. After discussions with
consultants WS Atkins and the DoT, the design was accepted and has
proved very successful.
While sheet piling has been required on a few locations, by far the
greater length of the new slopes between junctions 10 and 11 are
composed of reinforced soil. By the time Mowlem has completed its
œ35 million contract for the widening operation, a total
length of some 6km will have been constructed on both sides of the
carriageway. Some sections are as long as 800m and rise to a height
of 6m, the total surface area is about 20,000 m2.
Mowlem's engineers are somewhat cagey about the exact details of
the in-house design system which they have devised, beyond saying
that it conforms to the recent guidelines issued by the DoT, and is
designed for a life of 125 years. It is essentially a wrap-around
system using geogrids as reinforcement, wrapped around a selected
compacted fill, and with the topsoil retained by a geotextile
fabric.
Where the earth wall is acting to retain a cutting, no further
protection is needed. Where the new structure is being used to
build up an embankment to support the new hard shoulder, the face
is given an additional overall mesh cover to help retain the
topsoil. As a final touch, the whole surface is hydroseeded with a
variety of different mixes, carefully selected according to the
aspect of the slopes and their location. Other plants such as
clovers are included in addition to grasses, but are primarily
chosen for heavy root growth and short stems.
By using the system, Mowlem has been able to reduce the slopes from
the 1:2 of the originals to 1.5:1 or 60¼, creating sufficient
level ground to accommodate the new hard shoulder without the
expense and delays of additional land acquisition or heavy support
systems. It therefore offers considerable advantages in terms of
cost, and provides a more attractive and environmentally-friendly
final appearance.
Mowlem admits that it is labour intensive, which is something which
has to be taken into account when the contract has to be completed
to a very tight deadline and no night working is permitted. The
entire contract, covering reconstruction of the central barrier,
installation of lighting, all the earthworks, construction of the
new hard shoulder, erection of the noise barrier, installation of
new gantries and all the reinstatement work, covers only 44
weeks.
Construction started in February 1994 with the rebuilding of the
central barrier and installation of the lighting. By the end of
October the reinforced soil structures on the clockwise side were
virtually complete and the construction of the new hard shoulder,
much of it using recycled material in the lower layers, was under
construction. The anti-clockwise side will follow on through the
winter.
Over the contract there are 28 reinforced earth structures, either
cuttings or embankments. Because completion of these is a crucial
factor in the overall programme not all are constructed using the
Mowlem system. Some of the work has been subcontracted to Comtec
(UK) Ltd, which uses the Swiss designed Textomur system.
Although basically similar in form, this system uses a synthetic
geotextile to retain the topsoil on the face, which is further
strengthened by a steel mesh grid. The slope this produces is much
smoother, and, in the project manager Steve Lowder's view, results
in a much less natural appearance than with the Mowlem system.
'I think that by the time the vegetation has grown anyone driving
past won't be able to tell they are man-made slopes,' said
Lowder.
While construction has progressed well, there could be delays
ahead. The process is weather sensitive: 'If the moisture content
of the fill is too high you can't compact it,' points out Lowder.
With much of the work continuing until Easter next year, the
weather over the next few months could be an important factor in
finishing on time.
In addition to the extensive use of reinforced soil structures,
this section of the M25 has another claim to fame. The 13km of
sound barrier along either side represent one of the most
sophisticated road noise repression systems so far constructed in
this country.
Depending on the location, the barrier is either inclined at
10¼ to reflect sound upwards or vertical to reflect or absorb
noise. All types are supported on steel posts, fixed in individual
piled foundations up to 5m deep.
The barriers themselves, which reach a maximum height of 6.5m, make
use of four different materials - precast concrete panels, solid
timber panels, a proprietary absorbent panel system from Germany,
and transparent tinted acrylic. These are used in different
combinations according to the degree of protection from noise
required at specific locations.
The barrier installation, at an estimated cost of 15% of the
overall contract sum, is being carried out by Mowlem Civil
Engineering, in conjunction with Radian Systems.