Jubilee Line Extension contractors had to carry out emergency
nightwork last week as a tunnel breakthrough threatened to
undermine the foundations of a railway viaduct.
A 200t tunnel boring machine - named Tracey - emerged on the north
side of the River Thames last Wednesday two weeks ahead of
schedule. But the operation almost turned to disaster as the high
water table in the area - caused by January's heavy rainfall -
destabilised the ground at the tunnel portal.
The portal - on contract 110 of the JLE - is just a few metres from
the Docklands Light Railway viaduct and ground movement threatened
to undermine the structure.
Following on so closely from the catastrophic tunnel collapse at
Heathrow Express last year, this could have been another massive
body blow to the industry's image.
Contractor McAlpine - Wayss & Freytag - Bachy battled overnight
to sink a 20m length of sheet piling into the ground to protect the
foundations of the viaduct.
A ceremony marking the tunnel breakthrough was hastily cancelled by
the project team last Friday and rearranged for this week. The
statement said that the machine would surface this week instead. In
reality, the TBM actually appeared as expected last week but the
event was cancelled while water was pumped away from the site and
the emergency piles sunk.
A spokesman for the Jubilee project said: 'The event has been
delayed by water problems.' He did not comment on the piling around
the DLR.
The contractor set two TBMs going last August and called them
Sharon and Tracey. Both made excellent progress and Sharon broke
through with no difficulty on 20 December into a prepared 10m deep
and 10m diameter portal pit adjacent to the Docklands Light
Railway. The 1.2 km running tunnels have encountered sand and
gravel lenses in the clay - despite this progress has hit 154m per
week.
But as Tracey approached breakthrough in late January, engineers
feared that the wet ground - caused by this month's downpours -
could lead to the collapse of the DLR into the portal pit just
metres away. This prompted the emergency sheet piling. The TBM then
emerged into a 3m deep pool of mud filling the portal pit.