Aoki/Soletanche could face project over-run costs of more than
œ2 million on its Jubilee Line Extension contract after
failing to win a court's approval for an application to work an
extra two hours a day on site.
The jv - carrying out the œ70 million contract 105 between
London Bridge and Canada Water - wanted permission for the working
day on site to run from 7am to 7pm. This move was opposed by
Southwark Borough Council which favoured keeping hours to 8am-6pm
because the project runs close to residential property - some flats
are just 7m from its boundary fence.
In evidence put forward by Aoki/Soletanche's engineer, it was said
that with the shorter working day, the project would finish 4-6
weeks behind schedule, the penalty in the contract for late
completion being œ40,000 a day.
The jv would also have to stand the extra cost of the tunnel boring
machine, a further œ40,000 a day.
But a Jubilee Line spokeswoman said: 'The contractor says he will
finish on time and we have had no complaints about noise.'
Tony Garton, environmental protection officer at Southwark Borough
Council, said: 'We agreed to a 7am-7pm working day for a
seven-month period during the construction of the diaphragm wall,
but the contractor has now moved on to a further phase, concreting
the intermediate decks of the Bermondsey station structure.'
The authority has also approved exception days where a 10pm finish
was permitted during a concrete pour.
All five Jubilee Line contracts in Southwark were drawn up without
any reference to the local authority to see what working hours
would be permitted.