Balfour Beatty's hopes of restarting work on the central area of
the Heathrow Express by mid-February following the tunnelling
collapse in October last year have been dashed. The operation has
been put back several weeks because of problems in drawing up an
engineering solution.
Although still on the drawing board, the final plan will -
according to Heathrow Express - 'be a stronger design all
round'.
A spokesman said: 'With all the other facilities around - gas,
water and existing services - we must have a design that is robust.
Access is a difficulty: we have a large depth to go down, yet Car
Park Three is close by.'
Other parts of Balfour's œ60 million project are going well.
The running tunnel leading to the Central Terminal Area from the
north, being tunnelled conventionally, has driven 1km since
November.
Before the NATM tunnel collapse, the plan was to have a tunnelled
area ready to meet the tbm's first drive when it breaks through in
March. But now the contractor plans to detach the machine's shield
and skin and leave it in place while the tbm returns to the
beginning to start the final phase of the twin-bored tunnel.
British Airport Authority still hopes that the œ300 million
Heathrow Express project will be completed on time. It was running
four months ahead of schedule when tunnelling in the Central
Terminal Area worksite (Terminals 1,2 and 3) collapsed.
The insurance claim of œ50 million is the biggest ever on a UK
civil engineering project.