Central to the construction of the œ300 million Second Severn
Crossing has been the construction by Anglo-French joint venture
contractor Laing-GTM of two identical pairs of 137m-high concrete
pylons. With wind speeds reaching 180km/h, the supply of labour,
plant and equipment to this particular part of the project - now
almost completed - looked distinctly daunting.
Contractors Laing-GTM hit upon a solution from Peri, one of the
world's largest formwork manufacturers. Peri offered the
contractors an automatic climbing system designed to withstand
windspeeds of 180km/h. Peri's ACS75 system comprising 15t platforms
driven by two hydraulic climbing units proved a more attractive
option than slipforming.
The need to keep slipform shuttering constantly moving was
incompatible with both the geometrical accuracy of the cable
anchorages and the high density of steel reinforcement.
'The various angles of the anchorage guide tubes in the towers are
so critical to the job that they have to take precedence. We could
not have afforded to forsake that in order to keep construction
going so we quickly decided not to slip through the anchorage
zone,' said Second Severn Crossing project manager, Norman Haste.
'We also looked at slipping lower sections of the towers but again,
with reinforcement generally in excess of 400kg/m3 of concrete and
in some places close to 600kg/m3, which is quite dense steel, we
homed in on using totally independent climbing forms.'
Each heavily reinforced pylon is 4m wide with vertical upstream and
downstream faces to full height. The opposite sides taper from
10.2m at the base to 5.5m at a height of 77m, just below the lowest
cable stay anchorage point. Each tower has 80 precast concrete
cable stay anchorage units to accommodate the composite steel and
concrete bridge deck's 240 pylon cables. Each pair of towers is
braced by two 1200t concrete cross beams.
After concreting of the lower beam's two ends had taken place,
Peri's formwork retraction and climbing mechanism - pre-assembled
on shore - was put to work.
Wrapped round the outside of the towers the two sets of Peri forms
climbed independently in 4m shifts. Standard Peri shaft shuttering,
handled by crane, was used for each of the pylon's inner
walls.
The climbing shuttering, complete with six working platforms and
Alimak hoist access floor, hyraulically jacks itself up on a series
of climbing rails. These vertical rails are supported and guided on
special brackets bolted to anchors cast into the tower wall.
Climbing and securing each pylon's formwork before the next
concrete pour takes around 30 minutes.
Platform climbing speed is 0.5m/min and is performed through a
series of 640mm extensions and retractions of the sytem's
hydraulically operated climbing jacks. Regardless of the different
loads on each platform, the hydraulic control system automatically
monitors the flow to each jack and synchronises the climbing
mechanism to keep the platforms level.