Since the Court of Appeal decision in Pacific Associates Inc v
Baxter (1988) 16 ConLR 90, it has generally been assumed that the
court will deny the contractor a right of action against an
allegedly negligent architect or engineer whose under-certification
causes loss to the contractor. But it may be that the scene is
changing, and liability in tort is once again coming to the
fore.
Last year saw some significant cases on liability for negligent
misstatement, and the way is now open for more actions based on the
'reliance' principle of Hedley Byrne & Co Ltd v Heller &
Partners Ltd (1964) AC 465. Indeed, the architect/ engineer and
contractor relationship has always seemed to me to be a classic
example of 'reliance'.
The construction professional holds himself out as such, and the
industry's certification procedures are based on the certificate
and other decisions under the contract being made by a
professional. Further, as van Deventer says (Law of Construction
Contracts, 1993, page 223): 'It is obvious that in contracting, the
contractor relies on this professional, that he will not act
negligently in making his professional judgments; and in making
each application for a certificate this reliance continues.'
Such a simple analysis did not appeal to their Lordships in Pacific
Associates who regarded 'the contractual structure' as being the
central feature. That contractual structure, so they said,
precluded liability and meant that the contracting parties had only
their contractual rights against each other. Like Lord Simon in
Arenson v Arenson (1977) AC 405, I have always believed that the
primary role in one of responsibility.
Be that as it may, last year saw Judge Cyril Newman's decision in
Conway v Crowe Kelsey & Partners (1994) 39 ConLR 1, which
upheld the principle that a professional man may owe concurrent
duties to his client both in contract and in tort. In that case,
consultant engineers were sued by their clients for alleged
negligent investigation into structural damage arising from heave
under the plaintiffs' property and advice as to the necessary
remedial and preventive work which resulted, so it was alleged, in
the Conways suffering pure economic loss. The contractual claim was
statute barred.
Among other things, the judge held that the relationship of
professional and client is one of reliance. 'The relationship of
professional and client creates a relationship of reliance if not
dependence in which the client is less able to assess the nature of
the quality of the product (advice or a service) than in the case
of a supply of goods. [The relationship] is generally closer than
that of mere supplier and consumer or vendor and purchaser... The
client relies on the professional and her/his professed
expertise.'
Judge Newman was proved to have adopted the correct approach by the
decision of the House of Lords in Henderson & Others v Merrett
Syndicates Ltd (1994) 3 AII ER 506, which is of general
significance. The case concerned the claim made by Lloyd's 'names'
against their Lloyd's underwriting agents.
The House of Lords applied Hedley Byrne and held the underwriting
agents liable. Where someone assumes professional or
quasi-professional services for another person who relies on those
services, the relationship between the parties is itself sufficient
to give rise to a duty to exercise reasonable skill and care in
doing so. This does not depend on there being a contract between
the parties and Hedley Byrne liability is not confined to the
making of statements.
Interestingly, their Lordship held that 'indirect names were not
prevented by the chain of contracts contained in the agency and
sub-agency agreements from suing the managing agents in tort'. The
'contractual structure' was, accordingly, irrelevant.
The two leading judgments are masterly and, while Pacific
Associates was not considered by the Law Lords, the tenor of the
Henderson case casts serious doubt on the Court of Appeal's
analysis. Certainly, it is now clear that there can be concurrent
liabilities in contract and tort and the plaintiff can chose the
remedy which is more advantageous to him.
All professionals are under this concurrent liability. As Lord Goff
put it, 'as a matter of principle, it is difficult to see why
concurrent remedies in tort and contract, if available against the
medical profession, should not also be available against members of
other professions, whatever form the relevant damage may
take'.
In my view, the Court of Appeal's approach in Pacific Associates v
Baxter can no longer stand. Their lordships assumed that the issue
was a contractual one and the judgments appear to start off on the
assumption that no liability exists. The relationship between the
engineer/architect and the contractor is not subject to
negotiation: the contractor has no choice but to accept the
employer's nominee.
As van Deventer puts it (page 228), 'at the end of the day, the
construction professional effectively controls the project. He
wields enormous power over the contractor on a project, and his
decisions can make or break a contractor.'
The presence or absence of an arbitration clause in the contract
should not affect the position, although the availability of an
arbitral remedy seems to have been a factor in Pacific Associates.
The contractor may need additional safeguards - and as a long-stop,
a tortious claim against a negligent construction professional
provides him with that remedy. It is certainly available to him in
other countries of the common law and it should be available in
England as well.