Southern Water Services' solution to the need to clean up Ramsgate,
Sandwich and Deal beaches to EC standards is the œ56 million
Sandwich Bay scheme, a high priority project which eliminates 11
short sea outfalls.
The scheme involves creation of some 5,500m of stormwater tunnels
and pumping stations. Up to 860 litres/second will be pumped to the
scheme's treatment works, the new Weatherlees Hill wastewater
treatment works.
A high-speed turnkey contract by MJ Gleeson is due to complete the
plant for handover next April, less than two years after work began
on the greenfield site.
The contractor makes no secret of its belief in the design and
build approach. 'Doing more ourselves is the way to keep control,'
said Bob Jukes, director of Gleeson's Southern Construction
Division. 'It gives us more flexibility.'
Gleeson produced its own alternative design which won the contract.
By reorientating the site layout, it was able to eliminate a final
settling tank and reduce the aeration tanks, producing substantial
savings in the contract price.
The contract is a version of the IChemE Green Book extensively
modified by the client. Gleeson has now had several years' good
experience of such contracts with other clients and this helped
establish a similar rapport with Southern Water Services. However,
the contractor believes the speed of construction speaks for
itself. 'You would never build this plant as quickly with a
conventional contract,' said Jukes. 'It would have been 12 months
longer.'
He says such contracts give both parties an incentive to solve
problems. With all design (including M&E works) controlled
in-house, the risk of delays in one area holding up work in another
can be managed out.
Steel fixing apart, virtually all labour on site is Gleeson
employees working under the general foreman. The company believes
the advantages outweigh any losses from not sub-contracting the
work.
The plant's equipment is bought from suppliers and the contractor's
own M&E engineers manage its installation. Cables are laid by
its own electricians. Even the requirement to protect ductile iron
pipes with a winding of bitumen impregnated tape is done not at the
factory but on site by the contractor's site developed
apparatus.
The approach explains the presence of an Elba 30 batching plant on
site although, with a total concrete requirement of around
15,000m3, this is only just at break-even point. But it allowed
considerable precasting on site, avoiding the need to purchase
expensive proprietary items like primary settlement tank sumps. The
aeration tank bridge and baffle walls were also precast on site,
with items even cast for other sites.
The use of steel shuttering has given a very smooth finish to
in-situ concrete items such as settlement tanks. Steel shuttering
was fabricated for both primary and final settlement tanks, which
were both designed with the same 30m dia to minimise the shuttering
needed. This will now be available for future such castings at
other sites.
The plant's treatment technology is a fairly conventional fine
bubble activated sludge process. Effluent will first be screened in
an inlet building with full odour control. It will pass via a
detritor to four primary settlement tanks (seven hours' retention
at dry weather flow) and then be pumped to the four 4.5m deep
aeration tanks where air is pumped from the adjacent blower house.
The liquid then gravitates to four final settlement tanks (10 hours
retention at dry weather flow) before passing through a flap valve
to the 500m outfall into the tidal River Stour.
An environmental challenge was cutting the outfall across an SSSI
which meant careful replacement of topsoil and vegetation after
laying the 1100mm diameter ductile iron pipe.
Gleeson created extensive savings with the piling system created in
its redesign. Continuous flight augured piles were used on the
structures and the large piling platforms required were constructed
using imported hard core.
Pile layouts and loadings for the concrete tanks were redesigned
and the 1,700 originally proposed reduced by around a third. Tank
bases were redesigned too.
One major uncertainty was Southern Water Services' sludge strategy
which is still undergoing development but which necessitated a
change from sludge thickening to sludge pressing in mid-stream.