Implied terms are written into the contract by the Courts for
various reasons and there is no rule that terms cannot be implied
into standard form contracts. Indeed, even the most comprehensive
building contract will contain implied terms - which is a point
conveniently overlooked by many contract administrators who think
that the whole contract is contained in the four corners of the
documentation. In arbitration or litigation, the most difficult
thing is to establish that there is a breach of an implied term;
its presence is seldom challenged.
Terms can be implied into a contract by statute and custom and
usage, but in the construction industry the most important implied
terms are those implied by law and those implied from fact. A term
in these two categories will only be implied if the five conditions
laid down by the Privy Council in BP Refinery (Westernport) Pty Ltd
v Hastings Shire Council (1977) 52 ALJR 20 are met - at the very
least these conditions must be met if the term is to be implied by
law under the so-called Moorcock (1889) 14 PD 64 principle.
This means that the following conditions (which may overlap) must
be satisfied:
n The term must be reasonable and equitable.
n It must be necessary to give business efficacy to the contract.
No term will be implied if the contract will work and is effective
without it.
n It must be so obvious that 'if goes without saying'.
n The term must be capable of being clearly expressed.
n It must not contradict any express term in the contract.
The BP Refinery case arose out of a specially favourable rating
agreement between the Council and BP when the Council
unsuccessfully contended that the agreement was subject to an
implied term that the exemption was in effect personal. What their
lordships said, however, applies to terms implied in construction
contracts as well.
Terms implied by law are regarded as being 'a legal incident of a
particular case of contract' while those implied from fact are so
implied to make the contract commercially effective. Into the
latter category fall many commonly implied terms, such as the
implied term relating to co-operation. It is usually expressed as
being a term of a two-fold nature, as was the case in London
Borough of Merton v Stanley Hugh Leach Ltd (1985) 32 BLR 51.
In that case, Leach agreed with Merton to construct 287 dwellings
on JCT 63 terms. There was a dispute over late completion and
Merton contended that the delay was almost entirely due to lack of
diligence and care and lack of co-operation by Merton's architect.
Merton successfully established that the contract was subject to
implied terms that:
(i) Merton would not hinder or prevent Leach from carrying out its
obligations in accordance with the terms of the contract or from
executing the works in a regular and orderly manner; and
(ii) Merton would take all reasonable steps to enable Leach to
discharge its obligations and to execute the works in a regular and
orderly manner.
Leach v Merton has been followed time and time again and various
refinements are possible. The best judgment on implied terms is, to
my mind, that of Mr Justice Kaplan in the Hong Kong case of Jardine
Engineering Co v Shimizu Corporation (1992) APCLR 353 where it was
held that each of the several sub-contracts involve the subject to
an implied term of co-operation of the Leach type. In practical
terms, on the complex facts of the case, the effect was that the
nominated sub-contractors were entitled to claim disruption and
prolongation expenses even though the 'direct loss and/or expense'
provisions were not stepped-down from the main contract.
However, the judge rightly rejected the argument that terms should
be implied giving the sub-contractors rights to payment equivalent
to the main contractor's rights for complying with architect's
instructions issued under the main contract and giving them a right
to be indemnified by the main contractor in these circumstances.
These were not necessary in view of the major implied term and its
breach which mean that the sub-contractors were entitled to
reimbursement.
Mr Justice Kaplan upheld the contention that, on the agreed facts,
the main contractor was in breach of contract by depriving the
sub-contractors (however unintentionally) of their rights to have
the time within which to execute and complete their sub-contract
works in accordance with their sub-contracts. In so doing, he
followed the well-known case of Wells v Army & Navy
Co-operative Society (1902) 86 LT 764 where Lord Justice Vaughan
Williams laid down a vital rule:
'[W]here you have a time clause and a penalty clause it is always
implied... that the penalties are only to apply if the builder has,
as far as the building owner and his conduct is concerned, that
time accorded to him for the execution of the works which the
contract contemplates that he should have.'
Many other terms may be implied, dependent on the circumstances. On
the contractor's part, there is an implied term that he will
perform the work in a proper and workmanlike manner and, if no
time-frame is specified, that he will complete the work within a
reasonable time. But in practice it is most common for the claim to
be that the employer is in breach of such a term and every
well-drawn pleading in litigation or arbitration over construction
contracts contains claims based on breach of the usual implied
terms.