Donelon breaks through Bradford
Contractor
J F Donelon has completed the final tunnel drive of the œ4.2
million Bradford Basin phase 5 contract. The 760m drive of 3.66m
dia segmentally lined tunnel was excavated by a heavy duty shielded
roadheader in a scheme engineered by Bradford City engineers for
Yorkshire Water.