In round terms, there is a 5% loss in productivity for every five
hour increase in the length of the working week. The more prolonged
the period of overtime working, the greater the loss in
productivity.
This is one of the principal findings in the latest study in labour
productivity published by the CIoB.
It confirms the conclusions of research carried out by the US
Business Roundtable and by the European Construction Institute. The
ECI states that overtime as a variation on normal day work is the
most widely used pattern. It is the first resort of contractors
seeking to speed work. But it is the least effective. 'Scheduled
overtime working does not contribute to improved performance,' it
concludes.
And 'there is a danger that its use to overcome problems in the
short term will reinforce the industry's overtime culture, inflate
construction costs, and inhibit long term improvements in
performance.'
That 'overtime culture' is defined in terms of an average
construction working week of 45 hours, even in a period of
recession. In some sectors, notably civil engineering, the average
is still above 50 hours. That, in turn, indicates 60 or 70 hour
weeks being quite common.
European legislation to limit working hours may yet force a radical
rethink of this pattern.
The ECI suggests that shift working can provide a viable tool for
reducing project timescales, including double day shifts and
rolling shifts. At the same time, it is pointed out that there are
frequently practical constraints on the use of more flexible
working patterns.
'It is virtually a truism that productivity reduces during overtime
working as fatigue takes its toll,' commented the FCEC's David
Chapman.
'However, the nature of the job will dictate the working pattern.
Opencast coal mining can usually accommodate shift working. But
with road works, for example, you are frequently restricted in the
hours you can work. It is not like manufacturing. You just have to
make use of the time available. Then again, you have to weigh up
the additional managerial and supervision input that goes with
shifts.'
Chapman's case is vividly illustrated by the recent court ruling
which refused to allow contractors to work extra hours on the
Jubilee line. By the same token, client pressure has accelerated
innovative working patterns in the engineering construction sector.
And the high average level of hours worked on UK sites must raise
serious doubts.
George Henderson, TGWU chief, adds that there is a pay dimension
here. 'If you pay low basic rates, the men themselves demand the
long hours of overtime in order to get their earnings up to a
reasonable level,' he said. 'An example was the Thames Barrier
project where men were working up to 12 hours a day. We said that
was unreasonable. And three eight-hour shifts were introduced. This
lead to a strike over lost earnings. But the union stood firm
against the action, and rightly so.'