HOW HIGGS AND HILL SAVED 25%
œ40 million civils project - anonymity preserved at client's
request Changes to layout to access/agressœ2,600,000
Modified and improved structural
solution to assist in temporary worksœ1,850,000
Omission of structural works due to
changed layout and configurationœ1,600,000
Modification and change to internal
layouts, including cores, lifts
and escalatorsœ2,100,000
Changes to internal finishes without
detriment to specification and qualityœ270,000
Modifications to working methodology,
facilitating re-use of heavy equipmentœ2,500,000
Source: Higgs and Hill