Medway tunnel structure nearly there
The structure of the Medway tunnel is now just a month away from
completion following a series of major concrete pours by jv Tarmac
HBM on the œ70 million scheme.
Some 6,500m3 of concrete was placed in seven pours to form portal
base slabs and ballast for the approach structure. The structure
will be finished in May with the tunnel opening at the end of the
year after fit out.