A row is brewing between contractors and London Underground over
payment for claims and variations on London's massive Jubilee Line
Extension project.
Two contractors working on major parts of the œ1.9 billion
scheme have told CJ of problems with cash flow on the scheme and
have complained that design changes have caused many changes to the
work which they say so far have not been properly paid for.
But the project team has strenuously denied claims that there is no
dialogue or that payments are being deliberately held up.
JLE project director, Hugh Doherty, said: 'It is just not the case
that we are not dealing with the contractors' claims. If there is a
reasonable claim then the contractor must substantiate it to the
engineer who will then adjudicate. The key to resolving the claims
is proper substantiation by the contractors.'
But one contractor working on the scheme said there are 'serious
political stand-offs' on the project which they say could
eventually result in legal action.
'We are severely in debt on this project with a hugh quantity of
claims outstanding,' said the contractor. 'JLE is not honouring or
paying claims and this is a general problem.'
Another contractor explained that changes in design on the scheme
had been numerous. 'We will do the work but only if we are happy
that we will get paid,' he said.
Design changes are initiated by engineers' instructions which
contractors must then formalise by requesting variation orders
(VO's).
'There are VO requests which have been outstanding for nine
months,' said a contractor, 'and payment is even then considerably
delayed.'
Doherty agreed that there had been 'one or two areas where design
changes have occurred' but said that they can lead to different
views on how variations are dealt with. 'If the contractors are
having problems,' he said, 'they can come and see us.'
n Wimpey has been given clearance to work round the clock on two
elements of Contract 106 on the JLE project - the bridge beam
construction and trackwork.