Jubilee Line contractors on seven of the project's 10 major civils
packages are being forced to reprogramme work in a battle to make
up for delays and finish the scheme on time.
Just a year and a half after work on site began, contractors are
reporting delays of up to six months as design changes, poor ground
conditions and the ban on the use of the New Austrian Tunnelling
Method take their toll on project programming.
The Jubilee Line Extension project team maintains that the lost
time will be made up and the project will open on schedule in March
1998 and on budget at œ1.9 billion. But to do so will require
the contractors to either reprogramme works, work longer hours or
employ extra labour.
JLE project director Hugh Doherty, while refusing to confirm actual
delays on contracts, said: 'We have encountered problems in
different areas but across the project we are forecasting opening
on schedule. This is not to disguise the fact that there are
slippages but these can be addressed by taking up the float in the
programme, re-sequencing work or working longer hours depending on
the problem.'
CJ's inquiries have found that contracts 102, 103, 104, 105, 107,
108 and 110 are all behind in some areas.
Three of the largest tunnelling contracts (see box copy) have been
delayed by the ban on the use of NATM arising out of the collapse
of the Heathrow Express tunnel last October. 'The NATM issue was a
major blow for us,' said Doherty. 'But we do have plans to deal
with it. We have split the whole project up into separate packages
so we can address delays and stay on time.'
On Aoki/Soletanche's contract 105 between London Bridge and Canada
Water there is a 25 week delay, but attempts to work extra time on
site were scotched by the courts. 'We'll make up the time by
doubling up subcontractors in the finishing operations,' said
project manager Paul Haines. 'It is not ideal as we'd prefer them
to work sequentially.'
And on McAlpine/Wayss & Freytag/Bachy's contract 110 design
changes to the reinforced concrete box of North Greenwich station
has held up the work by four and a half months. And although the
two TBM's completed northbound drives on schedule, they have
immediately been held up on the westbound drives because approvals
from the Highways Agency to drive under the Blackwall tunnel were
delayed.
Doherty said: 'The machines were held up but the contractor has
worked 24 hours a day 7 days a week to get the first machine past
the tunnel and the second will go after Easter.'