The Department of the Environment is going green - and quickly.
John Gummer's energy efficient new residence is now just weeks away
from being complete.
Developed by Land Securities, the new Eland House in the heart of
Victoria in London, which will take over from the DoE's fading
headquarters at Marsham Street, has just 16 weeks left of its fast
track 88 week programme.
The building is notable for its use of environmentally friendly
technology but perhaps more remarkable is the way contractor Mowlem
is meeting the demanding programme through a co-ordinated use of
off-site prefabrication.
Land Securities had been looking for opportunities to develop the
site of the 1960s monolith which was the previous Eland House for
some time. It already had an outline scheme in place by autumn 1993
for a speculative office building when it managed to secure the DoE
as tenants.
At this stage Land Securities had already started negotiations with
Mowlem for the contract but suddenly the project took on greater
urgency. The programme which had been envisaged was accelerated to
meet the DoE's requirements and the energy efficient aspects of the
building which Land Securities had already considered took on
greater significance.
As a result Dave Rogers, Mowlem's project manager, and his team
found themselves on site, the morning after liquid celebrations for
receiving planning approval, contemplating a very rapid programme
for the œ35 million shell and core building. But while the
demolition contractor got going so did the Mowlem team.
To meet the demanding schedule, Rogers realised that construction
had to be kept simple, which was dependent on the design, and had
to work simultaneously on as many fronts as possible. 'One of the
key factors in achieving the fast programme has been going for a
very systemised method of construction,' said Rogers. 'But also as
the engineers were evolving the design we were working with them to
make sure it stayed within the parameters of fast building.' This
has very much been the crux of the project - a buildable design
geared towards the way Mowlem wanted to achieve the programme
through as much prefabrication as possible.
'Everything that we could think of that could be panelised,
systemised and built and tested in advance has been done on this
job,' said Rogers. This sort of co-ordinated approach depends on
good relations though and the open way in which client,
professional team and contractor have worked together has obviously
been essential.
'We had open lines of communication on the design of everything -
the frame, the cladding, the roofing - and it has really worked,'
remarked Rogers. 'If you're going to build this building in this
timescale everybody's got to have the right approach to doing it.
You have to adapt the design to fit in with prefabrication, but
clearly quality is the most important. We have to start with that
premise and then work out how we are going to make the concept fit
that.'
Mowlem generally and Rogers in particular has definitely taken a
liking to this way of building. This isn't the first time that the
company has done it this way but the technique has been very much
refined on this project. It isn't simply about prefabrication alone
though but also about the detailed planning which has been done
well in advance to make it work.
'There are a hell of a lot of meetings - often about things
happening off site - but all with the objective of making it simple
when it gets here,' said Rogers. 'Here it's just as important what
happens off site as what happens on site. There are days when I'm
the only one in the office because they [the Mowlem team] are all
abroad project managing their own little bit.'
The fact that they are abroad sourcing and checking materials for
what is going to be a government building is perhaps a little
ironic and unfortunate.
But while Mowlem was putting piles in the ground the team were
thinking about services, temporary works for the roof construction
ironmongery for the toilets etc. In fact, currently being installed
into the structure are the many prefabricated toilet modules which
Mowlem has had manufactured in Scotland. Complete and self
contained, the modules are lifted into place requiring just a link
up to the soil stack and services.
Equally significant in terms of prefabrication, and quite
innovative in terms of energy efficiency, are the prefabricated
cladding panels manufactured in Germany. They consist of glazing
and insulated panels with one window which has a sliding, motor
operated solar shade (a section of opaque glass) built-in which is
automatically activated when built-in sensors detect higher
internal temperatures. The sensors are linked into an overall
building management system which monitors temperature throughout
the building, the wind speed and the external temperature and
controls the shades as appropriate.
These cladding panels are being installed on the south, west and
east elevations in order to reduce the amount of solar gain in
summer and to maximise it in winter to maintain the correct
internal temperature. Although the technology isn't particularly
new it is believed to be the first time that it has been used in
this way.
These panels are just one element of the energy efficient and
environmentally friendly aspects of the building, which reduce
energy demand and which are giving the building a good score under
BRE's environmental audit scheme 'BREEAM'. Others include chilled
ceilings, a solar wall on the front elevation of the building which
absorbs heat and an independent generation plant. This is
effectively a gas fired engine which drives an alternator to
provide power at times of peak demand and which passes waste heat
into the system when it operates. This reduces peak demand supply
from LEB and sets the electricity loads within an accurately
predictable band.
In terms of engineering though, the most complex part of the
construction has been the foundations. With a Victorian sewer and a
London Underground tunnel running through the site this stage was
far from straightforward and involved piling around the
obstructions in such a way as to enable the structure to be built
to a regular grid above. 'Bearing in mind the difficulties in the
ground and the complexities of the foundations to get out of there
on programme was no mean feat,' remarked Peter Frackiewicz of Land
Securities.
Although the project started with this demanding engineering, the
key to its continued good progress has been the way prefabrication
has been embraced. 'It is certainly the fastest job of its size
that I have done,' said Rogers.