A Klemm KR 80302 anchor drilling rig from Ingersoll-Rand is being
used to drill holes for soil nailing on the A31 Ashley Heath Grade
Separated Junction contract near the coastal town of Bournemouth in
Dorset.
The soil nailing is being carried out by subcontractor BRC Mining
and Land Reinforcement on behalf of main contractor, Wimpey
Engineering and Construction.
It is part of a œ6.7 million contract to divert the A31 into a
cutting between retaining walls and under the Ashley Heath
roundabout at the point where the road meets the A338 Ringwood to
Bournemouth spur road.
The task, a central part of the contract being run for the Highways
Agency, provides earth wall support so that the contractor can
excavate vertical faces in the loose sand/gravel mixture underlying
the A31.
The 2,800-hole nailing project, one of the largest of its kind in
the UK, is said to minimise the amount of excavation and land
required for the scheme on a site where space is a premium.
Features of the crawler-mounted Klemm KR 80302 rig include a 200V
gear feed drilling mast with a Klemm0-4053A hydraulic drifter unit.
Additional equipment includes a Hiab 027 hydraulic crane for
handling large casings of up to 3m. If required, the unit's
hydraulics can run a water flushing pump.
On this particular project, Ingersoll-Rand's P600 portable
compressor supplies compressed air for air flushing in the drilling
process.
Soil nailing is a similar process to rock anchoring, where steel
bars are inserted into the face of an earth wall and grouted in to
tie the surface back and stop the wall from collapsing.
The construction of a vertical wall begins with excavation of
panels 12m long and one metre deep. For each 1m deep section, the
soil face is trimmed to make it vertical and then a layer of
reinforcing mesh is fixed to the trimmed soil face.
Sprayed concrete is then applied in a 100mm layer of concrete on to
the mesh which reinforces the face of the earth wall.
Sleeves are set into the concrete which can then be used as guides
for drilling through the concrete into the earth behind.
Once the drill hole has been formed using the Klemm rig, a 7.3m
long high tensile steel soil nail is pushed into the hole and
grouted in. A tightening nut on the exposed end of the rod anchors
the nail to the wall, tying back the concrete face. Once the first
1m deep section is completed, another metre is excavated and the
process repeated until the maximum depth of 8m is reached.
Details: enter 701 on card