'There wasn't much float before in the programme, but now there is
none.' Marcus Karakashian, senior supervising engineer for the
Jubilee Line Extension on contract 104, summed up the challenge
facing joint venture contractor Costain/Taylor Woodrow.
The œ76 million London Bridge station contract, part of the
œ1.9 billion Jubilee Line Extension project, was set back by
three months when tunnelling, using the New Austrian Tunnelling
Method (NATM), was suspended at the time of the Heathrow Tunnel
collapse.
Work was stopped voluntarily by the contractor, in consultation
with the HSE, although one year's work had so far produced no
causes for concern. Despite this delay, the contract, described as
the most complex of the project, has now been re-programmed to put
it firmly back on the rails.
At 208 weeks, this programme is the longest of the project to place
the work on London Bridge station right on the critical path.
However, not only does the contractor have to contend with this
pressure and an effective three month's cut in the programme
period, it is also having to work in the tightest conditions
possible - both underground and on the surface.
For the entire tunnelling workload the only point of access is the
shafts at Redcross Way - the focus for all the office
accommodation, stores, workshops and materials storage. Here there
is one large diameter shaft, used for personnel access, services
and cranage, and one smaller diameter shaft used for spoil removal.
Surrounded by a cramped working area, the two shafts are used for
the transfer of all workers, materials and equipment.
Everything radiates from this point - the contractor has to
construct a complex interchange between the new stretch of the
Jubilee Line and the existing Northern Line station, all squeezed
under and around the London Bridge railway station.
This involves driving eastbound and westbound running tunnels for
the Jubilee Line, constructing a station concourse, ventilator
shafts and a series of escalator shafts, cross passages and escape
shafts. At the same time, improvements are being made to the
Northern Line (otherwise known as the Misery Line) with a new
section of southbound tunnel enabling the old section to be used as
a station concourse.
'It's all part of working in London,' said John Wallace, the joint
venture's tunnelling manager. From the bottom of the shaft there is
a short cross passage to the Jubilee Line running tunnels. There is
also a 25m long, 11.3m diameter trial tunnel constructed at the
start of the contract.
Heading in the opposite direction towards the existing Northern
Line tunnels, a 50m long, 5.3m diameter trial tunnel was also
constructed. This was then extended into a 125m long access adit
for work on the new southbound Northern Line tunnel. This adit
joins the new tunnel close to the point where a step plate junction
is being constructed to bring the new and old southbound tunnels
together. As the two tunnels begin to meet, one larger diameter
tunnel is formed which then progressively steps down in diameter to
the point where the two coincide.
Work is currently under way at this point with the tunnellers (or
miners) working in extremely cramped, but dry, conditions. Using
pneumatic clay spades, the miners have excavated a large eliptical
chamber out of the London clay which is progressively lined with
spheroidal graphite iron (SGI) segments - claimed to be the first
section of eliptical tunnel in the country. The large chamber
surrounds the recently exposed Northern Line tunnel.
Looking as good as they must have done in the 1920s, the cast iron
segments of the tunnel firmly bolted together are exposed for
approximately 30m and look like an enlarged gas main. The 3.6m
diameter 'tube' rumbles at regular intervals as trains pass through
just a few inches away.
When the step plate junction is complete, the old tunnel will be
gradually dismantled leaving the trains running through an enlarged
chamber. But for the moment, the cast iron tunnel is supported in
concrete at the invert and by a series of steel frames braced
against the surrounding chamber. The miners are now working at the
narrow section of the step plate junction with very little room for
manoeuvre as they excavate around the tunnel. The face is advanced
3m before the next support frame is put in place.
The SGI segments are then located by some awkward manhandling and
the help of an air winch. The rate of progress here is just 3m a
week.
But work is progressing on other faces at a healthy rate using
various tunnelling techniques. 'For anybody who's interested in
tunnelling this site is ideal,' remarked Marcus Karakashian. 'We've
used nearly all types of tunnelling .'
This is partly due to the suspension of NATM working and the rapid
adjustments which had to be made by both client and contractor.
There was no way that both parties could wait for definite
conclusions from the HSE investigation into the Heathrow collapse,
so alternatives to NATM had to be sought and approved.
What actually happened was that some areas, such as the new
Northern Line station tunnel reverted to traditional tunnelling
methods. Others, including the Jubilee Line running tunnels,
adopted a revised NATM process which involves the normal techniques
of reinforced shotcrete but has the addition of a secondary lining
of in-situ concrete as a safeguard.
'Most of the changes were made with agreement of both sides,' said
Karakashian. 'But there were also many design changes.' Coping with
these changes, along with the lack of space and restricted access,
has, for John Wallace, been the challenge of the contract.
On top of that, maintaining the interface between the joint venture
partners has also been demanding. But both contractors and the
client are obviously sore at the need to change or abandon their
NATM working.
'We had been working for nearly a year without any problems,' said
Karakashian. 'NATM is much more flexible and has a far quicker
start up time,' agreed Wallace.
But all are apparently happy with current progress and insist that
the revised programme will be met. Although, ironically the new
NATM method is really no different than the old.
The primary lining of reinforced shotcrete is being left exposed
for some considerable time before the secondary in-situ concrete
lining is constructed - none of which is in evidence now.
However, as you would expect, careful and thorough monitoring of
earth pressure and movement is being carried out with, they claim,
no unexpected results to date.
The running tunnels are excavated using a machine with an
articulated boom which can accurately achieve the required profile.
The face is excavated as heading and bench, with the heading always
maintained 1m ahead of the bench.
When 1m of tunnel profile is exposed, a 25-50 seal- ing layer is
applied by the 'nozzle man' spraying the shotcrete. The mesh is
then placed with a lattice girder of 1m intervals, and the final
layer of shotcrete up to 150mm.
The shotcrete itself is a retarded dry mix with water and
accelerator added at the point of spraying, and is designed to
achieve 10N/mm2 at 24 hours, and 25N/mm2 at 28 days. For testing,
panels are cast in the tunnel and cores are taken every 24 hours.
In addition a photograph is taken of every joint.
The exposed tunnel face is also sealed with shotcrete every 1m, and
at weekends a full primary lining is applied. But full pressure is
exerted on the primary lining only when the tunnel's face is two
diameters away. The NATM is progressing surely and safely.
WHO'S WHO
Client:
London Underground
Contractor:
Costain/Taylor Woodrow
Technical Contractor:
Mott McDonald
Ground Treatment:
Keller Colcrete