Multi-party building contract litigation where the parties sue each
other and everyone in sight are still in vogue in Australia if the
immensely lengthy and complex judgment in Mutual Community Ltd v
Lorden Holdings Pty Ltd and Others [1993] APCLR 28 is anything to
go by. The judgment is largely factual but is worth reading from
for a number of reasons.
It has an excellent discussion of the concept of force majeure - a
term which is commonly used in UK standard form extension of time
clauses. In Mutual preliminary Heads of Agreement were said to
conflict with the standard contract entered into subsequently. One
term of the preliminary contract provided that 'extensions of time
shall be allowed only on the basis of force majeure'. The standard
term gave other grounds as well.
In ordinary usage, force majeure means 'superior force' or, as the
Oxford English Dictionary puts it, 'irresistible force or
overwhelming power'. The judge, Mr Justice Byrne, was firmly of the
view that the term 'does not appear to have a special trade usage
in relation to [building contracts] in the sense that the law will
permit a departure from ordinary usage'.
I have no doubt that he is correct. The term is, I suspect, widely
used because it is so imprecise. It has been imported from French
law and is used not only in the industry but also in international
sales contracts and shipping contracts. All the decisions underline
the importance of interpreting the expression in the context in
which it is found, often in the company of other related
expressions.
The best known case is Matsoukis v Priestman [1951] 1 KB 681, where
a shipbuilder was relieved from liquidated damages for late
completion for 'only the cause of force majeure and/or strikes of
workman where the vessel is being built, or the workshops where the
machinery is being made, or at the works where steel is being
manufactured for the steamer, or any works of any
subcontractor'.
A great commercial judge, Mr Justice Bailhache, declined to treat
the expression as meaning 'causes you cannot prevent and for which
are not responsible'. He did not attempt any general definition -
perhaps because definition is impossible - but he held that delays
due to breakdown of machinery and accident were covered by the
term. It did not cover bad weather, football matches or a funeral,
because 'these are the usual incidents interrupting work, and the
defendants in making their contract, no doubt took them into
account'.
The term is used in Clause 25 of JCT 80 and in the invaluable
Keating on Building Contracts, 5th edn., p576, the view is
expressed that it 'has a restricted meaning because matters such as
war, strikes, fire, weather and government action are expressly
dealt with in the contract'. Keating cites another well-known case
Lebeaupin v Crispin [1920] 2 KB 714, where it was said that 'any
direct legislative or administrative interference would, of course,
come within the term: for example, an embargo'.
In the Australian case, the discussion arose in the context of a
claim against architects and solicitors for alleged bad advice. The
complaint was not sustained, and the judge gave the term its
ordinary meaning. He could not extract from the document in
question whether or not the parties intended that the risk of any
particular delays might be taken into accout by them. In his
judgment, the use of the words force majeure 'is intended to permit
an extension of the completion date where delay is caused by any
event beyond the control of the builder and which by ordinary
prudent management it could not have avoided, except matters for
which it assumed responsibility under the agreement'.
Since the standard form contract alleged to conflict gave the
builder a right to extension of time for 'any cause or causes
beyond [its] control', the use of the technical words in the
preliminary agreement gave the builder no greater rights to an
extension than did the standard contract. The Australian standard
building contracts seem to be as badly drafted and verbose as their
English counterparts, as the quoted clause went on 'including any
act (other than any instruction of the architect as to a variation)
default or omission on the part of the Proprietor, the Architect,
any separate sub-contractor, employee or agent of the proprietor in
a manner which might reasonably be expected to result in a delay in
the works reaching practical completion'.
Other points of interest in Mutual Community Ltd v Lorden Holdings
include the fact that the court accepted the dual liability of an
architect to his client in contract and in tort and the discussion
based on the facts, of the extent of the architects' duties. In
Australia, as in England, it is an implied term of an architect's
retainer that the architect will exercise due care, skill and
diligence appropriate for a reasonably competent architect in
providing the advice or services he is asked to provide: Voli v
Inglewood Shire Council (1963) 110 CLR 74.
In all respects save two - advice on air conditioning in a proposed
building, and failure to specify certain items in sufficient detail
or to include a PC sum for them - the architect concerned had met
this standard and so was substantially off the hook.
Truth to tell, one's sympathies lie with the architect in this
instance. The project was an extremely complex one and appears to
have got off the ground with undue haste and the breaches
established were comparatively minor ones, eg, finishes. The end
result in money terms we do not know; the hearing was on liability
only.