In spring this year, the œ95 million Cardiff Bay Barrage
project came within an arm's length of catastrophe. But this is the
hi-tech 1990s: an arm's length was just what the designers had
planned.
A freak tide raised the waters of the bay higher than expected,
bringing the sea level terrifyingly close to the rim of the
colossal sand-bund cofferdam, within which all the costly
hydro-mechanical element of the barrage is being constructed.
With the sea-level just 750mm from breaching the oval-shaped
cofferdam, a few more knots of windspeed, a few more centimetres, a
few large waves, and the project's half-constructed locks and
sluices - not to mention the contractor's entire rationale at
Cardiff - would have been destroyed.
It did not happen - just as the tide forcasters, statisticians and
the probability boffins had said it would not.
Paul Neal, project manager of the Balfour Beatty-Costain (BB-C)
joint venture at Cardiff, has no grey hairs, though whether the
rest of the team survived similarly unblanched seems
unlikely.
high tide
"You can design these things to cope with a one-in-10,000 year
event," says Neal, "but would that be efficient? The dam here is
designed to cope with an unexpectedly high tide, and that's just
what it did."
The cofferdam is an amazing structure, roughly as big as the
barrage will be when completed.
Oval in plan, 350 metres long, 200m wide, and high enough to keep
out the 14m tidal range of the Taff Estuary, the the cofferdam is
so massive that it is difficult to remember that it is merely
temporary works. It effectively extends the shore out into the
estuary, and it could contain two Cardiff Arms Parks with ease.
Yet it was not part of the original design by consultant Sir
Alexander Gibb & Partners. BB-C believes that its inspired plan
to construct the cofferdam was instrumental to winning the
contract. Indeed, it must have taken a rare combination of nerve
and lateral thinking for BB-C's tender team to suggest such a
radical way of handling the project.
That was back in 1993. After pre-qualifying alone, Balfour Beatty
teamed up with Costain to win the project. Work commenced on site
in May 1994 after BB-C beat off competition from Laing, Tarmac,
Bouyges as well as a Kier, Christiani & Nielsen and Hochtief
group, a team of Taylor Woodrow and Robert McAlpine, and a pairing
of Trafalgar House with Ballast Nedam.
The 1.1km long barrage is designed to isolate the estuary reaches
of the rivers Taff and Ely from the tides and the sea. It will
create a permanent 500-acre, development-friendly, freshwater lake,
where now there are only tidal mud flats.
The barrage will run from Cardiff Docks on the East of the bay to
the residential area of Penarth to the West. The Penarth side the
barrage will feature locks, sluices, and the largest fish pass in
Europe. The creation of a new harbour to protect boats waiting to
enter the lake via the locks is also part of the contract.
island
It was originally envisaged that the locks and other major
structures would be constructed with the help of much smaller
"island" type cofferdams, sheet-piled into the estuary. If just one
structure was to be built, then this would have been virtually the
only method available.
But BB-C took the view that since there were several, large,
structures it was worth considering the more radical option. The
structures are three 10.5m by 40m navigation locks, the huge fish
pass, five massive sluice gates, and three hydraulically operated
bascule bridges to span the locks.
But there were at least three persuasive arguments against the
creation of the vast, all-encompassing cofferdam.
How, for example, would it be possible to create the encircling
bund in an estuary whose tides are so high, and so destructive? And
having constructed such a dam, would it not be in the way of the
final barrage? The counter argument was that the thing would be so
huge as to be uneconomical.
option
But having done its sums, BB-C decided it was by far the best
option, offering a number of important advantages. Most obvious, it
enabled the structures to be constructed in the dry, making that a
faster, quicker process.
A single cofferdam bund would also protect this element of the
project from the risk of bad weather. This is an important point as
the heavily-amended ICE 6th Conditions of Contract used on the
project do not give the joint venture contractor extension of time
due to delays caused by unworkable marine weather.
Another plus point for the bund was that, although the effort
involved in its construction - calling for colossal quantities of
sand, gravel and rock - much of the material could be re-used to
form the barrage proper after the cofferdam had served its
purpose.
Recalling the early days of the project, Neal says: "The dredging
went on 24 hours-a-day, seven days a week. We removed almost two
million cubic metres of alluvium."
To construct the cofferdam, dredgers bottom-dumped vast quantities
of sand won from the nearby Bristol Deeps. This filled the dam's
dredged foundation channel and then began to build up to form the
embankment.
Dredging activity was intense, as tidal flow naturally tended to
flatten the rising underwater embankment.
To help win the battle with nature, BB-C's subcontractor, Dredging
International, used one of the largest split-hopper dredgers in the
world, able to dump its shipments of 3,500 m3 in just 30 seconds.
"Licences for winning sand and dumping alluvium were secured by the
employer before the tender stage," says Neal. "It removed a lot of
uncertainty and risk, which would otherwise have been reflected in
the tender price."
BARGES
As the embankment rose in height, the barges could no longer float
above it, even at high tide. So sand was placed by pipeline pumping
and by "rainbowing" - where a sand and water mix is pumped out over
the sea in a well-aimed arc. A gap was left in the dam between two
relatively small sheet-piled structures and the sea flooded and
drained from the dam with every tide.
"The sand's natural angle of repose was a one in six gradient," he
says. "We needed it to be much steeper, one in three, inside the
dam. So at every low tide 18 machines headed into the cofferdam
from the shore and dozed up the sand. It was a race against time -
and the elements."
The cofferdam was also armoured with rock on the external, estuary
side, and to make it more impermeable a vib wall - effectively a
membrane of cement-bentonite has been inserted vertically from the
top of the bund.
"This involved vibrating an 800mm I-beam down through the sand and
injecting cement bentonite slurry through two pipes connected to
the beam," says Neal. "You form a contiguous and more or less
impermeable wall this way.
"Perhaps it wasn't strictly necessary: the barrage itself won't
have one. But we felt it would pay for itself in lowering our
dewatering and maintenance costs."
Work on the wall commenced in January 1996 and was completed in
April, allowing the cofferdam to be closed in May last year. The
dam was then further excavated so that piling for the major
structures could begin.
Examining these now half-built locks and sluices from within the
cofferdam is a strange experience. It is possible to forget that
they are founded beneath sea level, except, as Neal says: "When you
see a boat sail past above your head - that's weird."'
Three tower cranes and four crawler cranes are servicing the
creation of the concrete structures. The massive fish pass and five
controllable sluices are growing, plant-like, from a mix of steel
and timber formwork. The lock gates are not yet constructed, but
each leaf will weigh 44 tonnes.
Neal points towards a row of dewatering wells sunk into the sand
around the periphery of the site. Not surprisingly, no effort is
spared in this work. The computer-monitored outflow from the wells,
currently around 110 litres per second, is pumped up and over the
cofferdam. Markers in the sand walls are surveyed daily for trend
analyses.
emergency
Neal adds: "Emergency electrical back up is on hand to keep the
pumps working. If they didn't, and water table rose beyond certain
limits, the integrity of the dam would be doubt. We have a
full-time geotechnical engineer worrying about this."
But should the worst happen, and the cofferdam become unstable, an
evacuation procedure has been well rehearsed. "We can get everyone
off site within five minutes," says Neal. Much of the wider
project's design and programming has a similar, bomb-proof, feel to
it. It has also been heavily shaped by environmental
considerations.
The most important of these is a restriction on the movement of
construction plant through Penarth. It has meant that virtually all
materials have to come in by sea, or via the docks on the other
side of the estuary. BB-C tackled this by constructing the first
few hundred metres of barrage out from the dock side of the bay, at
the same time as constructing the cofferdam. A temporary steel
bridge was then constructed off the barrage to the dam.
So far, BB-C has poured 65,000 tonnes of concrete - the remaining
40,000 tonnes, and associated works to the structures, are
scheduled to be complete by the end of this year.
This activity is on the critical path of the project. The dam will
remain in place until the structures are complete. It is set to be
removed in early 1998.
"The sand will be re-used, much of it pumped across to form the
riverside flank on the dock side of the barrage," says Neal. "Once
we remove the sand the vib wall will disintegrate - so there are no
particular removal costs associated with that."
Of the dramatic and extraordinary cofferdam, there will be no
trace.n