Refurbishing large Victorian buildings is not everyone's idea of a
fun construction project, but for Chris York, project director with
John Laing Management, it's just what he's after.
"I'm so enthusiastic about doing this job. Not many people are
going to have the luck to renovate a Victorian hotel at one of the
foremost stations in London," says York.
Laing Management is now a year into its £45 million
construction management contract to refurbish the Great Eastern
Hotel at Liverpool Street, in the City of London.
"It's far more challenging and satisfying than building a new
office block - it's like fitting a jigsaw together," says York,
eyeing the hotel with a proprietal gleam.
A jigsaw accurately describes both the hotel's original
construction and its refurbishment. The Great Eastern was built in
the 1800s, substantially extended at the turn of the century and
has had a series of extensions and alterations since then. But
little or nothing has been done in the way of proper maintenance or
refurbishment in the last 20 years, which meant the hotel became so
run down it was no longer fit for use.
However, a joint venture between Arcadian Hotels and Conran
Holdings clearly thought that refurbishing the only hotel in the
City of London would be a lucrative prospect. They bought a long
lease from the freeholder - Railtrack - with the intention of
transforming the building into a five-star luxury hotel.
No easy task
Altering Grade II listed buildings is no easy task, but architects
Manser Associates, came up with a solution. "The architect has done
a magnificent job to get planning permission that ensures we create
a modern hotel within the old building," says York.
Manser's solution is to demolish the roof and fourth and fifth
floors, while retaining the building's distinctive corner and
central towers. The centre of the building has also to be
demolished down to sub-basement level and be rebuilt to create a
large central atrium with a glass roof. Two and a half additional
floors are to be created within the new copper-tiled mansard roof
raising the number of bedrooms from 150 to 266.
The ground floor will accommodate five restaurants, to be designed
by Conran Design Partnership, the new bedrooms are also being
designed by CDP. Conference and banqueting facilities will be
grouped around another new atrium on the first floor of the eastern
half of the hotel. A number of the finer rooms in the existing
building are being retained and a new front entrance will be
created.
Four new kitchens and new back of house facilities, such as storage
areas and staff offices, will be located at ground, basement and
sub-basement levels. Major plant is being installed at sub-basement
or roof level. The building will have to be totally re-serviced.
Bedrooms will be cooled by fan coil units and all the public areas
by ducted, chilled air. New lifts, new electrical, hot and cold
water and drainage systems and a cabling network for IT systems
will also be installed.
Laing won the job for a number of reasons, but a key factor was
that the client did not just want a construction manager, it wanted
an expert builder as well, something Laing could easily provide.
York was chosen as project director because he had worked on
Victorian buildings before. "Unless you have had experience of
these old buildings you might not find it interesting or easy. You
need to know the problems," says York.
Laing's immediate problem was that it was given no lead time to get
on site. "We had no time to plan," says York. The Great Eastern
Hotel shares a wall with Liverpool Street Station. Two levels of
shops on the station concourse run along this wall and reach back
under the hotel. Also, part of Liverpool Street Underground Station
is beneath the hotel.
All of this presented major problems for the demolition works. The
tower crane had to be installed in the middle of WH Smiths which
meant building a new shop for the retailer. A rubbish compactor and
service ducts had to be removed or re-routed and staff from London
Underground and the various other retailers moved out during the
initial demolition phase.
Demolition was carried out by John F Hunt who demolished the roof
and top two floors and then dismantled the central section floor by
floor with a small mini-digger to create an enormous hole in the
centre of the hotel. Trad Scaffolding installed a temporary Haki
roof over the hotel to allow work to proceed in the dry.
Structurally the hotel was largely in good shape. The project
consultants had been working on the hotel for a year and had
undertaken quite a lot of exploratory work, so Laing had a
reasonable idea of what to expect.
Corrosion
"The roof was shot. The lead work was gone and it had been adapted
and bodged around. There was some corrosion on the Victorian steel
girders, but there was very little dryrot in the breeze infiller
joints. Everything will have to be replastered, except for the
corridors. The weight is not an issue as we have demolished as much
as we are putting back on," says York.
Once the demolition of the roof and top storey was complete, Laing
began erecting the new steelwork which will provide the structural
basis for the new floors and new mansard roof. Steel was craned
onto the roof via a hole in the Haki roof and installation is now
complete.
While work is underway on the top floor, the basement levels in the
west block are also undergoing a thorough refurbishment. The
basement will house new cold storage rooms and staff preparation
and office areas. The existing configurations involve a lot of
twists and turns, so straight corridors are being cut and new
staircases being installed.
Lee O'Connor, Laing's manager for the west block, says: "There is a
damp problem on one level, so we are waiting for the architect to
come up with a solution, but there are no problems on the level
below. New drainage systems are now complete and some structural
steel has been put in to reinforce the ceilings as new plant rooms
are going to be installed on the level above."
The basement areas extend out under Liverpool Street Station's
concourse. A further phase of demolition will begin shortly to make
way for the new kitchens. This has meant decanting the shops on the
upper concourse level. The cantilevered walkway that gives access
to the upper shops has got to be propped during this phase of the
work. Work can only take place between 1am and 6am so as not to
disrupt the remaining shops and passengers using the railway and
underground.
Further along the concourse is the Hamilton Hall, a highly ornate
Wetherspoons pub. The hotel extends above the Hall and a careful
demolition job has to be carried out to remove the walls above the
Hall's main beams to make way for new conference rooms. Any heavy
handed demolition could send a decorative plaster cherubim crashing
down into someone's pint.
The main work on the central area has yet to come on phase. A new
reinforced concrete raft slab has been laid. Eventually a new
atrium will be constructed from the first floor to the top and
covered with a glass roof. New bedrooms will be constructed around
the atrium rising to eight floors.
York has set a tough schedule for his subcontractors of 20
bathroom/bedrooms a week. "We made it very clear to the M&E
guys and the plasterers that this was the speed we had to go at,"
says York.
York is keeping a watchful eye on tender and labour prices. "In the
market at the moment you can still get very competitive prices, but
you can get a very good firm for a much better price. If you get
the specifications right you should never have to compromise on
quality. The client is spending £45 million and he deserves a
£45 million building. Quality and time are linked together and
must not be compromised," argues York.
York acknowledges that now the industry is out of recession firms
are wanting to make profits of 5-10 per cent. "This is the pressure
we are under. Wages are going up so you have to know how to keep
people. If the demand is there you can't keep a lid on it, so you
might get poaching. You can counter that by providing a good
environment to work in, good canteens and so on.
"My style is to go round and get to know people on site. I do the
same with tenants and neighbours, talk to them, keep them
informed."
York is also strong on health and safety. "The planning supervisor
Mace, produced a good health and safety plan for the early stages,
one of the best I've seen in fact. We run heavy safety induction
courses with regular safety meetings and fire precautions are
rigorously imposed."
Laing started on site on 28 June 1997 and is due to finish on 2
August 1999. For York the biggest challenge is time. "It's a very
complicated job that needs a lot of understanding. We've a mountain
to climb. It will really test our skills and those of the
subcontractors to get it in on time."