The case of Norwest Holst Construction -v- Co-operative Wholesale
Society decided in the Official Referee's court earlier this year,
provides an opportunity to re-examine a number of interesting
points.
One of these is the basis upon which the re-measurement of
electrical and mechanical services should be carried out where the
subcontract incorporates drawings which show only schematic layouts
for the services.
Norwest Holst were main contractors for the construction of a
library at the John Moores University in Liverpool. CWS was
appointed subcontractor for the supply of labour, plant, materials
and consumables for the installation of the mechanical and
electrical services. The subcontract was broadly in accordance with
the familiar DOM/1 form for use with the JCT main contract
form.
extensive
The claims put forward by CWS were both large and extensive. These
covered most aspects of the work, both as to its proper valuation
and as to the time that the works should have taken to be
completed. In all, a sum of nearly £900,000 was claimed,
against which an arbitrator had awarded CWS approaching
£300,000 excluding interest.
Norwest sought to challenge this award and applied to the court to
have certain parts of the award set aside and other parts to be
remitted to the arbitrator, or for the arbitrator to give further
reasons. These applications were dismissed by the Judge in December
1997. There remained a series of questions of law to be tried on
appeal in front of his Honour Judge Thornton QC, one of which
concerned re-measurement of the works.
It was a startling feature of this dispute that neither party had
appeared to realise that the work was not to be re-measured until
after it had been completed. By that time, re-measurement on site
was impracticable as buildings were in occupation.
Here the drafters of the subcontract form are partly to blame.
DOM/1 provides a hopelessly confusing regime whereby at article 2
the parties may elect, subject to the provisions of the main
contract, that the subcontract is to be lump sum or re-measured. If
re-measurement is selected then clause 17 gives the detailed
provisions for the measurement and valuation of the work.
The provisions of clause 17 are complex, and unfortunately the
quantity surveying experts appointed by both parties had difficulty
in agreeing how these provisions were to work. The informal
intervention of the arbitrator in expert's meetings failed to
resolve these difficulties, and thus when the matter came before
the arbitrator he was presented with widely opposing views as to
how the subcontract was intended to operate.
The essence of the dispute was that the full extent, location and
layout of the pipework and cabling to be installed by CWS was not
shown on the tender drawings. What was shown was a schematic
representation of this work, consisting of straight line runs.
When work was carried out by the subcontractor, self-evidently
these were replaced by runs with bends and other deviations in the
layout needed to accommodate the layout of the building and its
contents.
The expert acting for Norwest took the rather bizarre position that
work in connection with bends and deviations and the like amounted
to "uninstructed work" and should therefore be ignored in the
re-measure. According to Norwest the subcontractor was responsible
for coordinating the mechanical and electrical work.
interpret
It had to interpret and price the work depicted on the schematics
and it should take the risk of costing the schematics accurately.
This was roundly dismissed by the arbitrator as nonsense. He quoted
clause 17(1) to the effect that "all work executed by the
subcontractor in accordance with the subcontract documents and the
directions of the contractor, including any directions requiring a
variation, shall be valued."
The fact that the works were being re-measured off as-fitted
drawings rather than as the works progressed, made no difference to
this analysis.
The work that the subcontractor had contracted to do was not only
that work depicted on the schematic drawings, but was embraced by
all the subcontract documents. This included the contract drawings,
the contract specification and all other contract documents or any
directions requiring a variation thereto.
His Honour Judge Thornton QC agreed that the arbitrator was
entirely right in this interpretation. "Thus it is only if the
coordination, interpretation and pricing undertaken by CWS yielded
work not required or envisaged by any and all of the contract
documents that it was varied work, which subject to any direction
by the main contractor, was not to be re-measured."
Furthermore, insofar as the arbitrator had determined that any
particular run of conduit or duct work was within the scope of the
works, although not clearly depicted on the schematics, the
arbitrator had made a finding of fact. Such findings were not
capable of being the subject of an appeal. Accordingly the appeal
was dismissed with costs to be taxed and paid by the main
contractor.