by Carol Millett
Fears that the troubled Jubilee Line Extension (JLE) will miss its
latest deadline have prompted London Underground to bring in
American construction giant Bechtel to ensure that it opens in time
for the Millennium Exhibition.
Meanwhile, the JLE's Westminster Station will definitely not finish
on time, London Underground told CJ this week. The station will
remain closed to commuters when the JLE is officially opened. There
is also a question mark over whether two other stations - Southwark
and Canary Wharf - will be completed by the official opening
date.
"Some stations will not be finished when the line opens next
spring," said the spokesman. "Westminster Station will effectively
be under a building site so for safety's sake will we keep it
closed until the new Parliamentary building is finished. There is
also a question mark over Southwark and Canary Wharf stations,
although we now think they will be completed on time."
Bechtel was called in by London Underground last month in a bid to
reassure Government ministers and the New Millenium Experience
Company that the line will be open in time for the millenium
celebrations. The company will be given a "six figure sum" to do
the assessment. It will be given total access to the length and
breadth of the project.
Bechtel have been given free reign on access and time. Bechtel's
fee has yet to be fixed. "It will cost whatever it costs. There is
no fixed figure." (See Comment, page 12).
, but it probably will be a six figure sum," said the
spokesman.
LUL insists it is confident it will meet its deadline but believes
it will not be taken seriously unless it is backed by an
independent assessment from Bechtel. by Carol Millett
Fears that the troubled Jubilee Line Extension (JLE) will miss its
latest deadline have prompted London Underground to bring in
American construction giant Bechtel to ensure that it opens in time
for the Millennium Exhibition.
Meanwhile, the JLE's Westminster Station will definitely not finish
on time, London Underground told CJ this week. The station will
remain closed to commuters when the JLE is officially opened. There
is also a question mark over whether two other stations - Southwark
and Canary Wharf - will be completed by the official opening
date.
"Some stations will not be finished when the line opens next
spring," said the spokesman. "Westminster Station will effectively
be under a building site so for safety's sake will we keep it
closed until the new Parliamentary building is finished. There is
also a question mark over Southwark and Canary Wharf stations,
although we now think they will be completed on time."
Bechtel was called in by London Underground last month in a bid to
reassure Government ministers and the New Millenium Experience
Company that the line will be open in time for the millenium
celebrations. The company will be given a "six figure sum" to do
the assessment. It will be given total access to the length and
breadth of the project.
Bechtel have been given free reign on access and time. Bechtel's
fee has yet to be fixed. "It will cost whatever it costs. There is
no fixed figure." (See Comment, page 12).
, but it probably will be a six figure sum," said the
spokesman.
LUL insists it is confident it will meet its deadline but believes
it will not be taken seriously unless it is backed by an
independent assessment from Bechtel.