by Kathy Watson
Jubilee Line Extension chief Hugh Doherty said this week that he is
"reasonably optimistic" that the delayed project will be fully
operational next spring, after successful trials of signalling and
computer software.
Doherty admits that increasing productivity levels is the key
concern but JLE would not give a firmer date for completing the
project despite the apparent new optimism. He has to increase
productivity to complete Westminster and other key stations on the
scheme.
Project sources told CJ last week that Westminster would not be
open when JLE goes into operation. Rising wage bills for M&E
trades and the opening date continually being pushed back have led
London Underground to call in US trouble-shooter Bechtel (See
Analysis, page 12-13).
Doherty told CJ: "We are running a number of trains under signal
control, so there is growing optimism. Three to four stations are
80-85 per cent complete but what we have to do is not technically
challenging. It is a question of getting the productivity levels
for building services."
He denied that cost had escalated to more than £2.8 billion,
which is a figure that he says he is comfortable with.
The Amalgamated Engineering and Electrical Union said it is in
talks with JLE over a new incentive scheme for its electricians.
National Officer Paul Corby is adamant they will not seek enhanced
wages unless they achieve greater productivity.