It is a common feature in construction contracts that where a
contractor intends to make a claim for additional time or money,
the contractor must first notify the employer or its
representatives of facts which may give rise to the claim as soon
as they become apparent.
The underlying objective behind these provisions is to provide the
employer with an early warning of likely problems so that steps may
be taken to reduce or eliminate their impact upon the progress of
the works.
Certain forms of contract, notably the New Engineering Contract,
develop these provisions further such that the notice requirements
are followed by steps which guide the manner in which the parties
must manage the issues giving rise to the claim by, for example,
convening meetings to develop solutions.
Deference
It is often questioned whether clauses which provide for the giving
of a notice in this manner can form the basis of a defence to the
claim in the event that the contractor has failed to give the
required notice. This question is often put another way. Is the
service of the notice a condition precedent to the remedy
sought?
Alternatively, it is thought that the failure to give notice is
itself a breach of contract which may give rise to a cross-claim
for damages if a claim should be brought.
These matters were recently considered in the case of Alfred
McAlpine -v- BAI (Run-Off) Ltd. McAlpine, as main contractor, had
obtained judgment against a subcontractor in respect of an accident
causing physical injury to a workman on site.
Before settlement the subcontractor became insolvent and
accordingly McAlpine claimed against BAI, as statutory assignee
under an insurance policy which had been held by the
subcontractor.
The insurance policy contained a term as follows: "In the event of
any occurrence which may give rise to a claim under this policy,
the insured shall as soon as possible give notice thereof to the
company in writing, with full details and as far as practicable
there shall not be any alteration or repair until the company have
had an opportunity of inspecting."
Such a requirement has much in common with the notice provisions of
claims clauses in construction contracts.
Notification
The first notification of the accident was not given to the insurer
until over a year after the accident had occurred. The court was
required to determine whether compliance with the notification
clause was a condition precedent to the liability of the
insurer.
Mr Justice Coleman considered that it was unnecessary that express
words should be used referring to the term as a condition
precedent, since this might be inferred from the context and other
provisions of the contract.
Firstly, he questioned whether the lack of notice would have a
prejudicial effect on the ability of the underwriters to manage and
defend the claim.
In addition, he noted that the insurer would have a remedy in
damages for breach of the contract notice provisions, providing the
insurer could establish that if it had been advised at the proper
time, it could have taken steps which would have altogether avoided
a judgment against the assured, or at least substantially reduced
the assured's liability for damages.
Taking all these considerations into account, it was held that it
was unlikely that the parties had intended that the notice
provision should be condition precedent to the insurer's liability.
This approach clearly reflected the decision in the case of Stanley
Hugh Leach -v- London Borough of Merton in 1985 in the context of
claims notices under JCT contracts.
Justice Coleman also considered that it was now generally the
practice to insert a term in insurance policies to the effect that:
"The due observance and fulfilment by the assured of all the terms,
provisions, conditions and endorsements of the policy insofar as
they relate to anything to be done or complied with by the assured
is to be a condition precedent to any liability of the insurers to
make payment under the policy."
Absence
In the view of Justice Coleman, the absence of such a term pointed
to a conclusion that neither party had intended such a provision.
It must be noted however that it cannot be said that such
provisions are commonplace in construction contracts.
Another pointer to interpretation of the contract would be where
compliance with the claims notification clause is not specifically
stated to be a condition precedent to the insurer's liability, yet
other particular policy terms are so expressed. Justice Coleman
considered that the omission of such express provisions in the
claim notification clause was a strong indication that it was not
the mutual intention of the parties that it should be a condition
precedent.
In conclusion, Justice Coleman was clear that in the event of
non-notification, while the insurer may be able to establish a
cross-claim for damages amounting to a complete set-off where it
could prove quantifiable loss in an amount equal to the claim, he
could not accept that proof of prejudice to the insurers could
itself operate as a complete defence in the absence of express
words to that effect.