It is common practice in main contracts to include a provision for
the deduction of liquidated damages in the event of delay. The
intention of such clauses is to pre-determine between the parties
the sum payable by way of damages in the event of a delay in
completion.
In contrast subcontracts rarely provide for liquidated damages in
the event of delay by the subcontractor. The primary reason for
this is straight-forward. An employer is in a relatively easy
position to compute the level of damages which it is likely to
suffer in the event of delay in completion of the project as a
whole. The main contractor on the other hand cannot readily
anticipate the damage it will suffer in the event of delay by a
subcontractor, for that damage will come from a variety of sources
dependent upon the nature, circumstances and timing of the delay.
suffered
The losses suffered by the main contractor may embrace damages
imposed by the employer, direct costs incurred in providing its own
additional resources, and claims from other subcontractors and
suppliers. The courts have been ready to intervene to enforce
liquidated damages provisions, recognising that there are benefits
to both parties in making such provisions.
In Temlock -v- Errill in 1987, the Judge said "there is every
reason why parties to building contracts should agree to liquidated
damages for non-completion. Proof of such loss is often difficult
to achieve and agreement in advance is a saver of disputes."
It has also long been recognised in the industry that the courts
will not enforce the liquidated damages provision if the sum
stipulated is found to be a penalty rather than a genuine
pre-estimate of the loss.
In the 1915 case of Dunlop Pneumatic Tyre Company -v- New Garage
Motor Company, the House of Lords set out the general principles in
this regard. It was held that whether a provision would be treated
as a penalty was a question to be judged as at the time of making
the contract, not at the time of the breach.
As a matter of construction, it was not relevant how the provision
was described in the contract, but it would be held to be a penalty
"if the sum stipulated for is extravagant and unconscionable in
amount in comparison with the greatest loss which could conceivably
be proved to have followed from the breach".
In the 1966 case of Robophone Facilities -v- Blank it was
determined that the onus of showing that the specified sum was a
penalty, lies upon the party who is sued for its recovery. These
matters were closely examined in the recent case between Ballast
Wiltshier and Thomas Barnes on appeal against an arbitrator's
award.
Ballast Wiltshier were main contractors on a project known as the
Arcades, Ashton-under-Lyne, and had employed Thomas Barnes as
subcontractors for certain reinforced concrete works.
The subcontract was in the form of a modified DOM/2 form, which in
its standard format contains no provisions for liquidated damages,
but at Clause 12.2 provides that after notice of failure to
complete on time, "the subcontractor shall pay or allow to the
contractor a sum equivalent to any direct loss and/or expense
suffered or incurred by the contractor, and caused by the failure
of the subcontractor."
In addition to this clause the parties had agreed a provision for
liquidated and ascertained damages in a separate numbered document
forming part of the agreement. This document identified three
sections of the works and rates for liquidated and ascertained
damages for each section were filled in.
counterclaim
These were precisely the same as the figures used in the main
contract between Ballast Wiltshier and its client, although the
sums appeared to apply to different areas. In its counterclaim
Ballast Wiltshier alleged wrongful delay in completion of the
subcontract works and claimed £1.96m as liquidated and
ascertained damages, or alternatively £146,000 as general
damages.
In his award the arbitrator recognised that the parties had freely
negotiated these terms but nevertheless held that the figures
inserted as liquidated damages were not reasonable estimates of the
losses that might be suffered by the main contractor in the event
of delay, and rejected the claim in its entirety.
On appeal, counsel for Ballast Wiltshier argued that it is often
reasonable for a contractor to estimate that the damages likely to
be suffered from breach of the subcontract by delay is the amount
of damages payable by the contractor under the main contract.
It was also argued on Ballast Wiltshier's behalf that the
arbitrator had mis-directed himself as to the burden of proof, in
that he had apparently failed to consider that it was for Thomas
Barnes to establish that the sums were a penalty. Counsel for
Thomas Barnes submitted that this had made no difference. He
asserted that the difference between the sums claimed for
liquidated damages and general damages was startling.
Moreover he argued that the agreed damages could not have been a
genuine pre-estimate of the loss, because not only were they the
exact same in amount as the sums in the main contract, but also
that they were in respect of different areas from the main
contract.
Hearing all of this, His Honour Judge Bowsher QC dismissed the
appeal, declining to disturb the arbitrator's award that the
damages were unenforceable as a penalty.