Steve Dempsey was cock-a-hoop when his fledgling company, Advanced
Demolition and Dismantling, won a £29,250 contract from Amey
Building to undertake a soft strip-out of an office building in
Stratford, east London.
That was last April. Dempsey recalls thinking that "working for a
blue-chip company like Amey" would put his one-year-old
Greenwich-based company "on the map".
Dempsey thought that if Advanced did the business on the Boardman
House project, not only would it look good to list Amey as a client
when tendering for other clients but it could also lead to getting
more work from £389 million turnover Amey.
Now, nothing could be further from Dempsey's mind and he is locked
in an acrimonious battle with Amey over payment. He vows that he
will never work for the firm again.
Dempsey claims that the scope of the work changed dramatically once
Advanced started on site and that this, together with other issues
outside of his firm's control, meant that what was intended to be a
two week contract ended-up taking seven weeks.
The first thing to change on the contract was the downsizing of the
originally intended 1.5 tonne capacity hoist to one with a payload
of 500 kg.
This smaller hoist was not made available until Advanced was into
the ninth day of its original 16 day subcontract. Even after the
hoist was commissioned, Dempsey reports that it was out-of-action,
via breakdowns or electrical supply problems, on 10 further days,
either for part or all of the working day, during the time that
Advanced was on site.
Advanced's managing director claims that downsizing the hoist meant
that it was taking "three times as long" to get rid of the stripped
materials from the building.
Dempsey says that power supply problems also caused hiccups
elsewhere on site. He claims that his workers weren't able to work
in the basement because the lighting wasn't working for the first
two-and-a-half weeks of the subcontract and likewise a goods lift
serving the basement was out of action until the end of the fourth
week.
After Advanced had entered its second week on site, the scope of
the refurbishment of Broadman House was altered to include
stripping out the old mechanical installations to make way for a
new air-conditioning system.
Previously the intention was to adapt the existing system. Another
firm was brought in to do the mechanical strip-out and tension
flared between the two demolition crews. Dempsey remarks: "We
didn't know there was going to be another demolition contractor on
site."
Hindered
He further claims that the new firm hindered Advanced's work, that
bottlenecks occurred, and that Advanced had to clear up some of the
other firm's mess.
The delays, alterations and additional work extended Advanced's
time of site from the original date of 8 May until 9 June. The
extra time on site caused Advanced cash-flow problems, as the
demolition contractor's surveyor Larry Sheen admits candidly: "The
level of funding was causing us distress." At a site meeting on 19
June, Dempsey says he told Amey: "Look we are being cash
starved."
Advanced has submitted a draft final account of £46,658
together a draft loss and expense claim of £36,693. In return,
Advanced has been paid £32,195 so far and Amey is offering
£42,000 for full and final settlement.
Dempsey has turned down this offer and is seeking arbitration. He
reasons that the roughly the same resources were employed over the
seven weeks and therefore the sum payable to Advanced should be
roughly three times the value of £29,250 for the original two
week contract.
Dempsey says that he was reluctant to submit the loss and expense
claim or revert to arbitration as he had hoped to reach an amicable
agreement. He says that his firm acted in good faith on numerous
issues such as undertaking the work without any drawings. "We
didn't get the drawings until the third week of the job - when we
should have been finished anyway."
Likewise, Advanced did not receive the amended DOM/2 subcontract
terms and conditions from Amey until after the original finishing
date - the firm has so far refused to sign the subcontract as it
does not like some of the contract conditions.
"I think we have been shafted. We had every right to walk off site,
but we stayed on. Now this." says Dempsey.
Requests
Despite several requests, CJ could not get a response from Amey.
However, CJ managed to track down Mike Turner a former site manager
on the Broadman House project.
Turner was an agency worker employed by Amey but he left before the
project was finished after a disagreement with Amey. Turner says he
holds no grudge against Amey. Turner argues that Advanced was "not
given a proper briefing and nobody knew the mechanical work was
going to be stripped out by another contractor."
Turner says the biggest problems were encountered on the third
floor where both demolition contractors were working alongside
one-another at the same time.
He explains: "Basically Advanced had no chance (to do the work
effectively)." He confirms: "No drawings were supplied to Advanced
until weeks into the contract."
Turner opines: "I don't think they (Advanced) were given a fair
crack of the whip."
He says Advanced "did try to get things done" and did not adopt a
confrontational approach. He thinks that the fast-track nature of
the project meant that Amey had little time "to put the project
together properly".