Performance bonds continue to cause considerable difficulty in the
construction industry. The 1994 case of Perar BV -v- General Surety
and Guarantee Company highlighted the difficulty that an employer
could face in seeking to obtain payment under a performance bond,
following the insolvency of its contractor.
It was held in this case that once the contractor's employment had
been automatically determined under the provisions of the JCT
contract as a consequence of the contractor entering into
administrative receivership, thereafter the contractor had no
obligation to continue with the works and therefore was not in
breach for failing to do so. Since the contractor was not in
breach, the surety did not become liable under the bond.
The practical effect of this decision was that in a circumstance in
which the employer most needed the bond, that is the insolvency of
the contractor, the bond proved to be unavailable.
Many commentators at the time blamed the archaic wording of the
performance bond and urged practitioners to use modern language to
explain and define more clearly the nature of the undertakings
contained in the bond.
It was also accepted that the JCT contract was at fault and
accordingly amendment 7 was published to JCT 81, the With
Contractor's Design form. This amendment revised the determination
provisions of the contract and added a new clause 27.8, whereby the
relevant provisions were now "without prejudice to any other rights
or remedies which the employer may possess".
Curiously, this particular clause had been in place in the JCT 80
standard form since amendment 11 published in 1992.
Armed with relatively clear language in the performance bond and
appropriate revisions to the JCT contract, it was assumed employers
might feel more confident in the security provided by such
bonds.
The case of Tower Housing -v- Technical and General Guarantee
Company proved otherwise. Tower entered into a contract with a
building contractor called Deltamar Construction in April 1995 in
the JCT 81 form. A performance bond was provided which stated that
"...in the event of a proven breach of the contract by the
contractor and/or in the event of the determination of the
contractor's employment under the contract for reasons of
insolvency, whether such determination is automatic or otherwise...
(the surety shall) ...satisfy and discharge the net damages
sustained by the employer as established and ascertained pursuant
to and in accordance with the provisions of the contract..."
The bond also went on to state that "nothing therein contained
shall oblige the employer to await completion of the works prior to
making any proper demand hereunder".
Administrative receivers were appointed to Deltamar prior to
completion of the works and new contractors were engaged under the
direction of the employer's agent to complete the works. It was
immediately apparent that the cost to complete the works in these
circumstances would be at least £80,000 in excess of the
outstanding balance of the contract sum, and that the surety would
therefore be likely to be asked to pay the full amount of the bond
of some £44,000.
In due course a claim was made for payment under the bond, and
faced with the refusal to pay, a writ was issued followed by a
summons for summary judgment under Orders 14 and 29 of the Rules of
the Supreme Court.
In affidavits in support of the summary judgment, the employer
presented an anticipated final account showing projected losses of
the employer in excess of the amount of the bond.
All of this appeared perfectly clear cut and yet His Honour Judge
Humphry Lloyd QC refused to grant summary judgment in respect of
the amount claimed. The difficulty lay in the fact that the
performance bond was drafted in such a way that the damages to be
recovered by the employer would have to be "established and
ascertained" properly in accordance with the building contract.
Since the final account for the completion works had not been
concluded this was not possible. The anticipated final account
prepared by the employer's representatives was insufficient for the
application of summary judgment.
Even the proviso that the employer could make a claim prior to
completion of the works could not help the employer since it too
required a "proper" demand to be made under the bond. No proper
demand could be made until the final account for the completion
contract had been prepared with all sums properly calculated in
accordance with the contract.
What then of the new clause 27.8 of the JCT contract? Unfortunately
this was not tested since it was not suggested by the employer that
there had been a breach of contract by the contractor which would
be the subject of this clause. It is doubted whether this provision
could in any event have the desired effect. Given that the contract
provides for the automatic determination of the employment of the
contractor upon the insolvency event, it would seem there can be no
opportunity for the employer to "accept" the repudiatory breach of
the contractor.
In consequence, despite the changes which followed Perar, it
appears that the employer may still be denied the intended use of
such a bond in the event of the most significant risk occurrence,
namely the insolvency of the contractor.