I recently reported the case of Ballast Wiltshier -v- Thomas Barnes
and Sons concerning the refusal to enforce an agreement for
liquidated and ascertained damages on the basis that the agreement
was construed as a penalty. This case also considered the payment
of retention monies.
Wiltshier were main contractors on a project known as The Arcades,
Ashton-under-Lyne, and had employed Thomas Barnes to do certain
reinforced concrete work on the project.
After conclusion of the works, disputes arose between the parties
which were referred to an arbitrator. At a preliminary meeting with
the arbitrator, the parties agreed that the arbitrator had
jurisdiction to consider all matters in dispute between the parties
whether or not those disputes had arisen or arose subsequently.
In its points of claim, Barnes claimed various substantial sums for
disruption, prolongation, late payment, overheads, loss of profit,
remeasured works, variations and dayworks.
In his award, the arbitrator found that Barnes was entitled to
extensions of time, totalling a further eleven weeks. He disallowed
some of the monetary claims made by Barnes and allowed others. The
claims allowed in the award were set out as gross amounts,
including retention monies.
On appeal to the Official Referee, Wiltshier submitted that the
arbitrator was wrong in awarding payment of retention monies.
It was argued on behalf of Wiltshier that payment of the second
half of retention money was not due until after the date of the
arbitrator's award, that the arbitrator had made an error of law in
determining the events upon which the retention was due to be
released, and finally that it was not within the jurisdiction of
the arbitrator to deal with retention money.
meritless
Frequently I report cases where it would appear that, admittedly
with the benefit of hindsight, the case put forward is plainly and
entirely without merit.
The worst culprits most recently have been insurers seeking to deny
payment under the terms of performance bonds. This aspect of this
case falls into that category.
His Honour Judge Bowsher QC remarked that even upon Ballast
Wiltshier's own case, the retention money fell due to be released
within days after the arbitrator published his award. He commented
that this dispute therefore had an air of unreality about it.
However, he was obliged to deal with matters which had been put
before him.
Firstly, it was argued on behalf of Wiltshier that the notice to
concur in the appointment of the arbitrator had made no reference
to retention money.
Judge Bowsher quickly dismissed this point, noting that the notice
to concur had referred to payments due under the terms of the
contract and that these terms included the provisions in respect of
retention money. Accordingly, he concluded that the notice
envisaged a review of the whole of the account between the parties
which necessarily included retention money.
Secondly, Wiltshier argued that the pleading of the case before the
arbitrator had not included a claim for retention money. Once again
this was dismissed.
The amounts claimed by Barnes had been the total remeasured value
for works in gross figures. In other words Barnes claimed a value
including the amount which Ballast Wiltshier was entitled to
retain. Judge Bowsher held that this was entirely consistent with
the subcontractor's rights under the contract.
action
When the sum due for payment under the subcontract falls due to be
paid, the party entitled to be paid has a cause of action for the
whole gross amount, irrespective of any possible retentions.
Clause 21 of the DOM 1 subcontract conditions provides that interim
and final payment shall be made to the subcontractor in accordance
with the provisions of clause 21.
In clause 21(3) the amount of the first and each interim payment to
the subcontractor shall be the gross valuation É less an
amount equal to any amount which may be deducted and retained as
retention by the contractor.
Judge Bowsher emphasised the use of the words "shall" and "may" in
these clauses. This meant that the subcontractor had a right to the
gross sum and the paying contractor had a discretionary right which
it may or may not choose to exercise to retain a part of that gross
sum. The sum retained is the subcontractor's money.
If retention is withheld it is withheld as security for any set-off
which may be raised, but the subcontractor has a cause of action
for the whole gross sum and it is perfectly entitled to claim the
gross sum without reference to retention money, leaving it to the
paying party to raise the discretionary right to make a retention
if it wishes.
Finally, it was argued that the arbitrator had misunderstood the
terms of the subcontract relating to the date for release of
retention.
Wiltshier argued that the agreement with the subcontractor had been
modified to the effect that the release of retention to the
subcontractor was conditional upon retention being released by the
employer under the main contract.
Judge Bowsher concluded that while the arbitrator had been wrong in
his interpretation of these clauses, the effect was of no relevance
and did not vitiate his award. Accordingly, the appeal was
dismissed.