Exclusive by John Leitch
The Amec/Alfred McAlpine joint venture working on a £100
million contract for the final link of the M60 Manchester Outer
Ring is reported to be seeking a six-month extension that will
delay final completion to 2001 - 18 months later than originally
scheduled.
Site sources also say Contract One is currently £40 million
over budget after the joint venture had previously been granted a
12- month extension of time because of an unavailability of
suitable material for a reservoir wall.
Miller/Kier's £49 million award, Contract Two, is said to have
been hit by "big claims". A spokesman for Miller denied rumours
that as negotiations had proved unsuccessful, Miller was about to
seek arbitration. "We got substantial completion on 12 December
1997 and are now into the maintenance period," said a Miller
spokesman. "I hope to see a progression of the final account in the
next few months."
However, insiders put the difference between Miller/Kier and the
client, the Highways Agency, at £20 million. "There are
several large claims still being negotiated over," said one.
Another commented: "Miller is not a stroppy go-getting contractor,
but it has raised the possibility of arbitration."
Miller/Kier had an enabling contract involving the redirecting of
services including both foul and clean water. Electrical junctions
had to be rejigged. Liquidated damages imposed on the contractors,
who finished the work in April this year, six months late, are said
to run to some £1 million.
Contract Three, a £18.9 million project awarded to Costain, is
complete and the final account is agreed. This week both Costain
and the HA were tight-lipped over the size of the cost
overrun.
The last of the four contracts was awarded in May this year, to be
built by Balfour Beatty by June 2000. A change in policy at the HA
has led to Contract Four being offered on a design and build basis.
The winning price of £50 million raised eyebrows as the
official estimate was £75-100 million.
Steve Edwards, Highways Agency project manager, said this week: "We
awarded it to Balfour at that price because it was good value for
money. Under the terms of the contract the contractor assumes the
vast majority of the risk. I expect it to be built for that
price."
Asked if the cost overrun of the Amec/Alfred McAlpine contract was
£40 million, Edwards said: "£40 million is closer to the
overrun for all the contracts, the total figure." As CJ went to
press, no one at Amec was available for comment. Edwards said
progress was being made on the Miller/Kier payment. "It has not
been resolved but it is resolvable. The account is progressing
well."