Oresund contractors last week claimed that they can finish the
Danish immersed tube tunnel on time, despite an element being
flooded and sinking last month.
The 57,000t tunnel element suffered only minor damage when it sank
and is to be used as planned in the permanent structure. Oresund
Tunnel Contractors (OTC) has refloated the 176m-long concrete
element and next week plans to ballast it into final position in a
seabed trench. Construction has been at a standstill since the
accident.
OTC is building the 3.5km-long tunnel off the Danish coast, near
Copenhagen, as the western link in a Danish-Swedish transport
project. The tunnel is being built from 20 precast concrete
elements by the contracting group, which includes John Laing
Construction, but the 13th tube element sank during final
ballasting operations in August.
Seawater punched-in one of the bulkhead doors and damaged another
after the failure of a temporary concrete support. OTC assistant
project director Niels Uldall said the base plinth support failed
because of "human error" - a U-shaped rebar support was omitted
during fabrication.
Uldall said the production system has been tightened up. "We've
introduced some new 'hold-points' for physical checks at different
stages of fabrication." He said the client's All Risks insurance
would pay for the construction recovery work.
This week OTC focused on repairing the foundation bed that was
damaged by the sinking element. The element had been fitted with
some replacement bulkhead doors, dewatered and refloated to be
taken some 200m away to await completion of foundation
repairs.
OTC is using one immersion pontoon to place the tunnel elements.
The pontoon has remained connected to the element because removal
would have been difficult and unnecessary as the January 1999
installation deadline should be met, said Uldall.