The cost of the Jubilee Line Extension is set to soar after London
Transport chief executive Denis Tunnicliffe said financial
resources will be provided for "what it takes to finish" the
project.
Tunnicliffe would not put a figure on the costs required to
accelerate work to enable the troubled project to meet its
rescheduled completion date of September/October 1999 - more than
18 months late and with a lower spec signalling system.
The original budget price for the work was £1.7 billion. Last
Friday, Tunnicliffe said the cost would be at least £2.75
billion. One day later transport minister Dr John Reid said the
bill would be "in the region of £2.9 billion". Industry
sources suggest that the final cost could be £3.5 billion, or
higher, once the costs for accelerating the work and settling the
claims made by JLE contractors are taken into consideration
Last week, the 1,000-strong JLE project team was rocked by
Tunnicliffe announcing that project director Hugh Doherty was
quitting and that US construction manager Bechtel was taking over
to ensure the project was finished in time for the millennium
celebrations.
Doherty will be replaced by Cliff Mumm, a senior vice president of
Bechtel. Mumm will be bringing in between 25-30 Bechtel staff to
handle the project. Mumm said "possibly half a dozen" senior JLE
staff could also be leaving. He added that Doherty will be "my
adviser for a day or two."
Tunnicliffe would not reveal Bechtel's fees but these are likely to
run into several million pounds. The US firm will also receive an
undisclosed incentive sum if the JLE is completed to the
rescheduled programme. This calls for the extension to open in
three stages - Stratford to North Greenwich by 30 April 1999, North
Greenwich to Waterloo by the end of August 1999, and Waterloo to
Green Park by September/October 1999 - only weeks before the
Millennium Dome is due to open.
Tunnicliffe said "the rate of completing stations over the summer
had been disappointing" and this was one reason for the works
slipping further behind schedule. He defended Bechtel's appointment
by saying: "It is not unusual to bring a new team in to re-energise
a project." He said the project is "some 90 per cent complete" and
that "to deliver the project next year, we needed more
resources."
LT has also abandoned plans to get the "moving block" signalling
system working in time for the millennium.
l See Comment on page 16.