Exclusive by David Nunn
The Ministry of Defence is to undertake a massive overhaul of its
procurement methods that will place its £1.7 billion
construction programme with a handful of companies within three
years.
The move is part of an ambitious aim to make the MoD the "leading
driver" in reforming construction, taking over the mantle from the
likes of BAA. It follows a review of MoD procurement by the new
chief executive of the Defence Estate Organisation, Ian
Andrews.
Under Secretary of State for Defence John Spellar will unveil the
policy in a hard hitting speech at next Tuesday's Defence Estate
Organisation Conference for Industry
"It is likely to be a pretty hair-raising event for the industry.
We have decided to tell it like it is," said Clive Cain, director
of defence works at MoD.
At the heart of initiative is a move to slash the number of
contracts the MoD lets from the present level of 800 per annum and
establish single point responsibility from cradle to grave.
The ministry will switch to a system of prime contracting where
work will be parcelled up into large chunks and let to a single
organisation that takes responsibility for procuring it to the
MoD's specification. The move is likely to downgrade the position
of consultants and architects.
Work will be bundled up into parcels in the region of £250
million. By giving out such sizeable packages the ministry believes
it is giving the industry a real chance to partner with suppliers
and subcontractors. "There are two tiers to partnering. We have to
enter into partnering agreements with the industry, and then the
industry has to partner with the supply chain. This will allow both
to happen."
The MoD hopes that by concentrating purchasing power among a few
prime contractors it will be able to bring about a 30 per cent
reduction in costs, saving £500 million per annum.
The ministry expects to see standardisation emerging in different
facilities built by the same prime contractor. This would apply to
things like wet central heating, pitched roofing, steel frames,
windows and electric lighting.
Cain said there would be competition in the new regime. "But it
will be between a few companies. There might only be eight
companies capable of doing this sort of work, but that's the
industry's problem - not ours.
"We are fed up dealing with the whole industry. Why should we have
to?"
The MoD is reorganising its business units over the next six months
in readiness for the new procurement regime, which will cover all
activities, not only construction.
The new procurement policy will take effect from 1 April next year.
"Over a three-year period we would like to turn our entire
programme over to prime contracting," said Cain.
Over £1 million has been spent researching the changes, which
follows Building Down Barriers, in which MoD trialled partnering on
two projects with Amec and Laing.