It will come as little comfort to learn that the shipbuilding
industry suffers its fair share of disputes on cost and time
overrun. Judgments in connection with shipbuilding contracts have
often provided important guidance in the law of contract generally,
of direct relevance to construction contracts.
The case of Stocznia Gdanska -v- Latvian Shipping Company decided
recently in the House of Lords provides an example.
The appeal to the House of Lords arose out of proceedings relating
to six shipbuilding contracts, each for the construction of a
single refrigerated vessel. Stocznia was a Polish shipbuilding yard
which contracted to build the ships for Latvian Shipping. Under
each of the contracts Stocznia undertook to design, build, complete
and deliver the vessel, such that property would not pass to
Latvian until delivery.
instalments
The price for each ship was between US$27.6 million and US$29
million. Provision was made in the contracts for the price to be
paid in four instalments. Broadly speaking these were: (a) 5 per
cent advance payment against a bank guarantee, (b) 20 per cent upon
receipt of a notice of keel laying (this was defined as meaning
that the first and second sections of the vessel's hull had been
joined on the berth where the vessel was to be constructed, (c) 25
per cent upon notice of successful launching of the vessel, and,
(d) the balance of 50 per cent upon delivery of the vessel.
Work began on vessels 1 and 2 in 1992 and the first instalments of
5 per cent of the price for all six vessels were duly paid. However
by July 1993 agents for Latvian revealed that they had serious
funding difficulties. By December 1993 they had informed Stocznia
that taking delivery of the vessels might be impossible.
Whilst these discussions and exchanges were taking place, progress
on vessels 1 and 2 had continued and in December 1993 the keel of
the first vessel was laid and the corresponding notice issued.
Payment against that notice was not made and therefore Stocznia
issued a notice rescinding the contract in accordance with its
terms. The same happened three months later with vessel 2.
There then followed, to put it mildly, a series of controversial
events which would stretch the imagination of even the most
hardened construction industry commercial manager.
Stocznia decided to take advantage of the keels laid for vessels 1
and 2 in order to trigger the second instalments, first for vessels
3 and 4 and then for vessels 5 and 6. The purpose of Stocznia doing
this was plainly to secure accrued rights to the second instalments
for all four of these vessels, thereby putting itself in a stronger
financial position than it would have been if it only had a right
to claim damages.
simplicity
Stocznia's approach was one of astonishing simplicity. The keels
which had originally been laid in connection with the contracts for
vessels 1 and 2, were simply re-numbered for vessels 3 and 4 and
fresh keel laying notices were then served.
To nobody's surprise, the second instalments for these vessels were
not paid and accordingly Stocznia gave notice rescinding the
contracts for these two vessels. Exactly the same procedure was
then followed in respect of vessels 5 and 6, appropriating the same
keels to the contracts for these two vessels and serving keel
laying notices in respect of them.
Predictably, these instalments were not paid and again Stocznia
gave notice of rescission of both contracts.
Space does not allow me to report the tortuous litigation route
that then followed. However, in front of the House of Lords, the
issues which had to be addressed included firstly, whether Stocznia
had acquired accrued rights to the second instalments of the
contract price in respect of vessels 3 to 6, and secondly, whether
the right to be paid by instalments in any event fell away once
Stocznia had given notice of rescission of contract.
On the first of these points, Counsel for Stocznia pointed out that
what triggered the obligation to pay the instalment was not the
keel laying as such, but the giving of a notice that the first and
second sections of the hull had been joined on the relevant berth.
Their Lordships saw little merit in this argument. Lord Lloyd of
Berwick noted: "My instinctive answer, and that which would I think
be given by any fair-minded man, is "of course not." There only
ever were two hulls, how can two hulls be made to serve the purpose
of six contracts? The re-numbering of the hulls was an artifice to
enable the plaintiffs to recover six keel laying instalments when
they had only laid two keels."
Dealing with the second point, Counsel for Latvian argued that once
the contract had been rescinded by Stocznia, it had no rights of
common law to recover unpaid instalments of the contract price.
Lord Goff of Chieveley held that this was contrary to principle,
and he could find no contractual expression of an intention of the
parties to this effect.
Stocznia were entitled to sue for the unpaid instalments in respect
of vessels 1 and 2, notwithstanding that they had rescinded both
those contracts.