On 9 October 1998 it was announced that the term 'Official Referee'
is to be dropped with immediate effect. The Official Referees Court
is now to be known as the Technology and Construction Court.
Judges are no longer to be known as Official Referees but as Judges
of the Technology and Construction Court. The jurisdiction of the
court effectively remains the same and includes any claim which
involves issues or questions which are technically complex.
In what appears to be the first judgment made under the title of
the Technology and Construction Court, between Ahmad Al-Naimi and
the Islamic Press Agency, his Honour Judge Bowsher QC was asked to
consider an application for a stay of proceedings in accordance
with section 9 of 1996 Arbitration Act.
Section 9 concerns the powers of the court to stay (effectively
suspend) court actions until the disputed matters are decided by an
Arbitrator.
arbitration
Section 9(1) provides that "a party to an arbitration agreement
against whom legal proceedings are brought may apply to the court
to stay the proceedings." Paragraph 9(4) provides "on an
application under this section the court shall grant a stay unless
satisfied that the arbitration agreement is null and void,
inoperative, or incapable of being performed." Ahmad Al-Naimi
(trading as Buildmaster Construction Services) entered into a JCT
Minor Works contract to undertake alteration and refurbishment
works at a property in Buckinghamshire belonging to the Islamic
Press Agency.
The contract expressly excluded works of a second fix and finishes
nature, but it was alleged by Al-Naimi that a subsequent oral
contract had been entered into under which second fix works had
been carried out. Disputes arose concerning payments due, and the
nature of the agreements entered into by the parties. The
employer's contract administrator and the contractor produced sworn
affidavits giving conflicting accounts of their respective
dealings.
Al-Naimi contended that whilst the first contract did contain an
arbitration agreement in the standard form, the subsequent oral
contract did not contain an arbitration agreement. This contention
was particularly important to him because he would be able to
obtain access to Legal Aid to conduct these proceedings in court,
whereas Legal Aid would not be available to him in an arbitration.
specified
Counsel for the Islamic Press Agency countered that either the work
carried out had been specified under the original contract, or it
was the subject of a valid variation to that contract. In either
case the arbitration agreement would apply.
Reference was made to the 1997 decision in Halki Shipping
Corporation -v- Sopex Oils Limited. In that case the court had to
decide whether all disputes, whether genuine or otherwise, would
fall to be decided by an arbitrator where section 9 of the 1996
Arbitration Act applied.
It was decided that the term "dispute" should be given the widest
possible interpretation.
The judge stated, "All that the charterers have to do is to say
that they dispute the amount due, or indeed to fail to pay
anything. In either of those events there is in ordinary language a
dispute as to the amount due."
Elsewhere in the judgment, the Judge stated that he was of the
opinion that, however indisputable the plaintiff's claim, there
remained a dispute between the parties which they had agreed to
refer to arbitration. It followed that the defendants were entitled
to a stay of the action under section 9(4) of the Arbitration Act
1996.
In considering the present case, his Honour Judge Bowsher QC
appears to have taken a rather softer approach by questioning
whether there were "genuine disputes" between the parties.
On evidence put before him he was satisfied that there were indeed
genuine disputes concerning the construction of the original
contract and, for example, whether certain items of work fell
within the description of work contained within that original
contract.
There could be no doubt in his mind that those disputes were
disputes which the parties had agreed should be submitted to
arbitration, and they were therefore not matters for decision by
the court. Accordingly, he ordered that the proceedings be stayed
for arbitration. This meant that the first issue for the arbitrator
to decide would be to construe the original agreement between the
parties. In other words, the arbitrator would be required to decide
which, if any, of the disputes between the parties were disputes
arising in connection with the original contract, and therefore
within his jurisdiction.
If the arbitrator were to decide that any matters disputed between
the parties were beyond his jurisdiction, then the stay on
proceedings could be lifted to enable the claim with respect to
those disputes to be pursued in the courts.
Such a procedure was entirely consistent with section 30 of the
1996 Arbitration Act which gave the arbitration tribunal the
competence to rule on its own jurisdiction.