It should have been the crowning glory of Welsh Rugby, and a
feather in the cap of its constructor, John Laing. Instead, the
£121 million Millennium Stadium in Cardiff is proving a garish
advertisement for the shortcomings of both parties.
Inadequate decision making, poor planning and naivety on both sides
has left the project running £20 million over budget. Even
worse for rugby lovers, the project may not be completed in time
for the Rugby World Cup in June 1999.
It has now emerged that Welsh fans may have to trek all the way to
France, in what would be the final ignominy for their national
game.
A spokesman for Le Stade confirmed to CJ that the Welsh Rugby
Football Union has made contingency reservations for next June as
doubts grow over just how much of the stadium Laing will have
completed by then.
The extent of the project's disarray was revealed last week, when
Laing was forced to make a stock market announcement disclosing
contracting losses of £26 million. The worst offender was
Laing's civils division, which has notched up losses of £23
million - £20 million of which are attributed to the
Millennium Stadium.
Laing's woes at Cardiff are sounding an ominous note for lump sum
contracting within the group. The loss-making design and construct
job has proved the final straw for the Laing board, which has been
growing increasingly disenchanted with the high-risk and low-return
of mainstream contracting. The grand failure of Cardiff has now
crystallised thinking in the boardroom and led Sir Martin and his
men to sound a strategic retreat toward the relative safety of
management contracting, partnering and forms of fee-earning
construction.
A £7 million reorganisation is under way that is expected to
cost many employees their jobs, not least the managing director of
civil engineering, Tony Evans, who is tipped to depart next
month.
The reorganisation will see the unlikely bedfellows of building,
civil engineering and management contracting divisions combined
into one neatly packaged unit. Together with clearing away any
outstanding contractual liabilities, this can only reinforce
speculation that Laing is preparing to sell its construction arm,
possibly leading to an orderly break-up of the family construction
group.
From all of this it is apparent that the Millennium Stadium project
is going to have unusually widespread ramifications. But what has
caused it to go so disastrously wrong? Industry sources cite "a
catalogue of cock-ups" for which both client and contractor bear
some of the blame.
The story begins with a spat between the Welsh Rugby Football Union
and the Cardiff Rugby Football Club. The two organisations have
neighbouring grounds - so close, in fact, that they share a party
wall in one of their stands.
That this wall would be demolished was a given in the design
proposals drawn up by WS Atkins, and which were later novated to
Laing under the design and construct contract.
In the event, the Welsh RFU failed to win agreement to demolish its
neighbour's south stand.
Gareth Davis, chief executive of Cardiff RFC says: "We have an
integral stand between the two clubs, and the Welsh RFU told us
they wanted to knock our stand down. This is by far the largest
part of our ground, so we asked them what the other options were
but they had none."
At Cardiff's recent AGM it emerged that negotiations had been
underway for two-and-a-half years to solve the problems of the
development. It is clear that the club feels the Welsh RFU has been
high handed and intransigent, and is now paying the cost: "Eighteen
months ago we were told we were not needed and they went away and
decided to build around us, but they now have problems," reflects
Davis.
The Welsh RFU's decision to 'go it alone' meant Laing cranes could
not oversail the Cardiff site. It also meant plans for the new
stand had to be redrawn, calling for substantial additional
steelwork and concrete to support the retractable roof.
non-performance
But Laing's construction plans - and lump sum price - were
contingent on demolition going ahead. It argues that this, and
other late design changes, amount to non-performance by the client,
and possibly WS Atkins and American architect Lobb.
The case is yet to be proven. Ultimately it may be an arbitrator
who apportions blame - and some form of legal action is pencilled
in for next year. But whatever the outcome, it is possible to
wonder why Laing did not spot such a glaring risk to its
construction strategy. Instead, through a combination of naivety,
good intentions and eagerness to win a prestige job - it appears
Laing simply rushed in to the project without looking hard
enough.
A spokesman admits: "Fundamentally we had a design which was not
much more than a conceptual scheme against which we made a
judgement - and which demonstrated that we made that judgement far
too early in the design process."
That is not to say the contractor has no case for additional
payment. Laing is adamant it will recoup at least some of its
£20 million costs.
Part of its argument will be that the client made other, as yet
unspecified, design changes at a late stage.
Meanwhile, industry sources allege that part of the cost overrun is
due to Laing's choice of Italian firm Cimolai as steel contractor.
It is a relative newcomer to the UK, with only three major jobs
under its belt, and therefore not the most obvious choice for a
difficult contract.
Indeed, Cimolai made a less than auspicious start in the UK with
the late-running Gade Valley Viaduct, in the final section of the
M25. Delays in the completion of the steel bridge in turn delayed
the opening of the entire M25. The entire project team was
criticised by the National Audit Office.
Cimolai then went on to work with Laing, for the first time, on the
second Severn crossing.
It is said that disputes ensued, and it is claimed that as means of
settlement Laing agreed to use Cimolai on the Millennium Stadium
project.
Both Laing and Cimolai refused to confirm or deny the suggestion.
But Laing did state that Cimolai has ISO 9002 quality assurance
certification that is recognised by British certification
bodies.
This cuts no ice with the UK steelworks fabrication industry, which
claims Cimolai does not understand UK construction or standards. A
large number of firms within the industry spoke to Laing before it
awarded the contract and forewarned that problems would
arise."
Such comments may be no more than a predictable attempt at
protectionism by UK steel companies. Nevertheless, the Italian
steel fabricator is running seven weeks late. However, it is
holding Laing to blame and has issued a claim against the
contractor for insufficient and delayed design information. Corado
Ceresatto, project manager for Cimolai, says in explanation: "It is
a very difficult and technical job." However, he refused to comment
further.
Last week Laing Construction chairman, David Blair said this claim
had now been settled and added that he was hopeful of claiming much
of the money back - implying the fault did not ultimately reside
with Laing.
Laing's main objective now is to finish the job on time, and so
extricate itself without further embarrassment.
The last thing it wants is to be remembered as the bodging builder
responsible for sending lucrative World Cup fixtures to
France.
A spokesman says: "It will not be entirely complete by June 1999,
but that is not the current intention. The intention is that by
June 1999 it will be sufficiently complete to allow a match to be
played between Wales and South Africa. It will then be
progressively completed so that it will be ready for the Rugby
World Cup. We are working towards a date in August 1999."
Last week Laing appealed to Cardiff County Council to lift noise
restrictions and allow it to work 24-hours-a-day,
seven-days-a-week, claiming that the stadium would otherwise be
impossible to complete on time.
Meantime, it is trying to minimise the effects on neighbours. A
Laing spokesman says: "We have invested in new monitoring
equipment, which will reduce noise levels. "The council have also
taken up our offer of providing secondary glazing for all
neighboring residents," but he refused to put a figure on the cost
of glazing.
limitations
The use of extended shift working brings up the issue of compliance
with the Working Time Regulations, which has imposed new
limitations on working hours. So far there has been no hint of a
repeat of the Jubilee Line, where electricians are accused of
'blackmailing' employers on the late-running project.
There is one further thorn in Laing's side, however. The company is
also in dispute with the Welsh Office about the £3 million
necessary for a river walk which is essential if the stadium is to
receive a safety certificate for its 72,500 capacity. The Welsh
Office has yet to pay the money because it wants to be represented
on the board of the Millennium Stadium PLC.
The Laing spokesman says: "Obviously we can't be happy that we have
a project which is going to cause substantial losses. And therefore
if we could turn back the clock we would very much like to, but we
can't.
"We are looking at the extent to which other people ought to be
contributing towards mitigating those losses, and at present we are
committed to completing the project."
In the meantime the rugby world watches and waits.