London Underground (LU) will have to pay up to £1 million in
legal costs and compensation after losing its High Court bid last
week to claim damages from a civil engineering firm over delays on
the Jubilee Line.
LU claimed that design changes at Canning Town Station, made by the
civil engineering contractors Kenchington Ford of High Holborn, put
the project behind schedule and threatened full public access to
the Millennium Dome at Greenwich.
However, Kenchington Ford claimed it had to go to considerable
expense to comply with the changing design demands of the tube
operator.
It was claimed that LU was undecided about whether the Jubilee Line
should run alongside the Docklands Light Railway or that one line
should run above the other with full passenger access between the
two at Canning Town.
There was also an argument about the construction of concrete
slabbing to separate the Docklands and Jubilee platforms, and
altercations over plans for the drainage system.
After the High Court hearing a spokeswoman for Kenchington Ford,
said: "We are pleased with the decision, but are disappointed that
London Underground saw fit to take it to trial."
A spokesperson for LU said: "Naturally we are pleased the
contractor's fees have been substantially reduced.
"As to our own claim, LU were advised to bring the case as a lot of
public money was at stake. We are very disappointed with the
judgement and we will have to consider it carefully."
In his 150-page judgment His Honour Judge David Wilcox described
the Jubilee Line extension from Green Park to Stratford, East
London, as "one of the largest civil engineering projects in
Europe.
"It was initially planned that the line would be completed in the
Spring of 1998 at a total cost of about £2.1 million. The
project is late and the costs exceed the budget."
Judge Wilcox ruled that there had been faults on both sides during
the construction period, but he charged LU in excess of
£500,000 in legal costs, and awarded only £66,650 to LU
for any shortcomings on the part of Kenchington Ford. The civil
engineering contractors were awarded £384,808 for losses
suffered as a result of the actions of LU.
LU now has the option to appeal but it refused to speculate as to
what its next step would be.