A considerable proportion of construction litigation these days
concerns a client taking action against its professional advisers
to recover moneys paid to a contractor in respect of a claim for
delay and disruption.
The extent to which a sum reached in negotiated settlement with a
contractor can form the proper measure of damages against a
professional party is the subject of much debate.
The 1951 case of Biggin -v- Permanite is often cited in support of
the contention that where the client can show that the settlement
with its contractor was a reasonable one, the amount of that
settlement may be taken as the correct measure of damages in the
third-party proceedings.
This issue was further clarified in the case of P&O
Developments -v- The Guy's and St Thomas' National Health Service
Trust recently heard in the Technology and Construction Court.
contracts
The action arose out of a part of a new building development at
Guy's Hospital in London. The employers, Guy's, had employed Higgs
and Hill as management contractor who in turn had entered into
numerous works contracts.
Guy's also employed a management team which included P&O
Developments as project managers and Austen Associates as
mechanical and electrical services engineers.
There were delays to the project in respect of which the architects
granted extensions of time. By 1994 the project was in disarray
with costs rising.
At that point Guy's took advice from Davis Langdon and Everest who
recommended a commercial agreement or 'wrap-up deal' with Higgs and
Hill.
Following that advice an agreement was made between Guy's and Higgs
and Hill in December 1994 by which Guy's agreed to pay Higgs and
Hill £83.9 million.
The agreement made no reference as to how that money was to be
applied by Higgs and Hill, and in particular did not dictate what
sums, if any, were to be paid to individual works contractors. The
report of Davis Langdon and Everest had, however, made provision of
individual sums for the claims made by the works contractors.
Guy's claimed against P&O and Austen for having caused a part
of the project delays by producing late and inadequate information.
It was contended on behalf of Guy's that the settlement figure was
primarily derived from the advice of Davis Langdon and Everest and
that was as far as Guy's needed to go in order to establish the
reasonableness of the settlement.
The provisions made by Davis Langdon and Everest should thus be
taken as the starting point for the computation of the damages
claimed against the consultants.
The consultants on the other hand contended that that would be far
too simple an approach and that a much deeper enquiry should be
made to establish the relevant damage incurred by Higgs and Hill
and its works contractors.
In other words it would be necessary to look behind the face of the
advice to examine the workings and working papers of Davis Langdon
and Everest and to investigate whether the advice given was in fact
correct.
A series of preliminary issues were agreed to be tried in front of
his Honour Judge Bowsher QC.
reasonable
Judge Bowsher was asked to consider how Guy's might prove that the
global settlement was reasonable. Was it sufficient that Guy's
relied on advice given by competent advisers, or would it be
necessary to investigate whether the advisers themselves acted
reasonably in giving that advice?
Judge Bowsher confirmed that both strands of evidence would be
relevant to arriving at the correct measure of damage.
In answering these questions Judge Bowsher was particularly wary of
the term 'reasonable' in this context. He emphasised that the
question was not whether the plaintiff had acted reasonably in
settling the claim, but whether the settlement was a reasonable
one.
Furthermore it was necessary to clarify the rule in Biggin -v-
Permanite. The rule was firstly one of evidence. In other words,
the settlement may provide some evidence of the value of a third
party claim, but it may not be conclusive. Such a settlement did,
however, set a maximum to the third-party claim.
valid
The second rule in the case Hadley -v- Baxendale was also apposite.
This meant no more than that the parties may be held to have had in
reasonable contemplation those damages that flowed from the
settlement of legally valid third party claims.
Finally it was asked, if Guy's are able to prove that the
£83.9 million global settlement was reasonable, does it follow
that the components of that sum allocated by its advisers to the
individual works contractors represented Guy's actual loss with
respect to those works contractors?
If not, would it be necessary for Guy's to prove that the sums
allocated against each works contractor were in fact reasonable
sums?
If this latter proposition were true, would it then be material to
investigate the settlement figures that Higgs and Hill had
subsequently adopted to close down the accounts with the works
contractors?
Judge Bowsher was clear that the allocation against works
contractors deriving from the Davis Langdon and Everest report
could not be used to determine Guy's actual loss. He held that it
would be necessary for Guy's to prove those sums as reasonable
amounts in respect of each works contractor.
The actual settlement figures as between Higgs and Hill and the
workscontractors would merely be evidence of that reasonableness or
otherwise.