The manner in which public works contracts may be awarded within
the European community is tightly controlled under EC law.
European Community Counsel Directive 93/37/EEC and its predecessor
Directive 71/305 detail the procurement procedures which a public
authority is obliged to follow when intending to place public works
contracts with a value in excess of the stated financial
thresholds.
The intention behind these directives is to introduce a degree of
transparency in the awards procedures operated by public works
authorities, such that non-compliance with EC competition and
anti-discrimination law, for example, may be more readily
controlled and challenged.
The latest directive allows 'open', 'restricted', and in limited
cases, 'negotiated' procedures to be followed. In the latter of
these two procedures, the authority is required to undertake a
pre-qualification procedure for contractors prior to the tender
action.
The pre-qualification criteria by which a contractor may be
assessed are strictly controlled by the directives. These criteria
include proof of the contractor's financial and economic standing,
and its technical knowledge and ability.
The case of Ballast Nedam Groep-v-Belgian State examined the manner
in which the pre-qualification process would be applied in respect
of holding companies. Ballast Nedam was the dominant company in a
group of companies registered in the Netherlands. It had been
pre-qualified and registered on the relevant Belgian list for
recognised contractors for public works.
registration
In 1989 however the Ministry of Public Works in Belgium refused to
renew Ballast Nedam's registration on the basis that it could not
be a works contractor in accordance with the Belgian rules because
"Ballast Nedam appears to be a holding company whose major assets
consist of shareholdings in subsidiaries. It is apparent from
references submitted regarding works carried out that the latter
were in fact executed by various subsidiaries."
The Belgium Ministry of Public Works had concluded that Ballast
Nedam was therefore to be regarded as a separate legal entity from
other group companies, and as it did not itself have the necessary
technical capabilities, was not suitable for registration.
Ballast Nedam challenged this decision in the relevant Belgian
court. Applying a procedure set out in article 177 of the EC
Treaty, the court turned to the European Court of Justice for
guidance on interpretation of the relevant EC directive.
In January 1997 the European Court of Justice replied to the effect
that the relevant directives were to be interpreted as permitting
account to be taken of companies belonging to a group for the
purpose of assessing the criteria applied to the dominant or
holding company of that group.
It was for that holding company to establish that it actually had
available the resources of those companies which were necessary for
carrying out the works. Accordingly it fell to the Belgian court to
assess whether such proof had been produced in the proceedings
between itself and Ballast Nedam.
decision
This decision, while helpful, did not satisfy the Belgian Ministry
of Works. It wanted to know whether the effect of the decision was
such as to impose an obligation on it to take into account the
resources available to a dominant company where those resources
belonged to other group companies. Alternatively, it wished to
establish whether, as the awarding authority, it still had a
discretion to refuse registration even if the dominant company
could show that the necessary resources were available to it.
If it were true that the public authority could exercise a
discretion in this regard the effect on public procurement
legislation would be considerable. Holding companies might become
unable to pre-qualify for public works contracts even though the
combined resources of its group and subsidiary companies would be
more than adequate for the relevant projects. This would present
considerable difficulties to such companies since the separate
legal entities of the subsidiary companies might not individually
have the necessary resources.
Similarly this would bring an end to the practice whereby groups of
independent contractors can seek registration on lists of
recognised contractors on the basis that they will form joint
ventures or other legal entities for the purpose of carrying out a
public works contract, if awarded a contract after the
registration.
The decision of the Court of Justice will however prevent such an
unfortunate conclusion.
In a judgment handed down in December 1997, the Court of Justice
confirmed that the relevant directives were to be interpreted to
the effect that a body authorised to assess applications for
registration to a member state's list of registered contractors for
public sector contracts, is under an obligation, when assessing an
application for registration from a dominant company in a group of
companies, to consider the resources necessary for carrying out the
contracts which are actually available to that company from
companies belonging to the group.
As a consequence, companies can rely upon the resources of their
subsidiaries in applying to be listed for public works contracts,
providing they can show that they actually possess the necessary
control over the resources of the subsidiary companies.