Exclusive by Graham Ridout
Some leading main contractors have been accused of callously
exploiting loopholes in the construction Act to extend payment
periods to subcontractors and put obstacles in the way of going to
adjudication.
John Huxtable, chief executive of the Confederation of Construction
Specialists, said he had examined the forms of contract issued by
more than 50 main contractors and that all of them "partially or
completely" ignored the spirit of the Act.
The Act came into force in May and was intended to give
subcontractors surety on payments, by stipulating when firms are
paid and telling them how much they will receive. The Act also
gives firms the right to suspend work within days in the event of
non-payment, and the right to speedy adjudication of any
grievances.
Huxtable said that one of the common ruses was to "push back the
due date for payment." Under a standard DOM/1 subcontract, the
maximum period that a subcontractor would have to wait from
starting on site to receiving payment is 48 days - 31 days from the
start date to the due date plus 17 days from due date to
payment.
In the subcontract conditions issued by Shepherd Construction,
payment will "become due 42 days after the end of the month in
which the application for payment for the interim payment was
received by the contractor (Shepherd)." Huxtable calculated that
this could mean subcontractors had to wait up to 78 days - 31 days
to the end of the month, then 42 days to the due date, then five
days to payment.
Gordon Ray, Shepherd Construction's commercial director, said: "We
obtained specialist advice in advance of the 1998 DOM/1 reprint to
ensure that the update of our standard subcontract amendments were
strictly in accordance with the provisions of the Act, whilst at
the same time protecting our established commercial
position."
Shepherd's contract was drafted by leading law firm Masons. Ray
added that an update of these standard amendments will be
implemented at the turn of the year.
Huxtable said that other major contractors were using similar
conditions to those employed by Shepherd.
Clauses covering a subcontractor's right to suspend work are also
being tampered with, Huxtable said. Under the Act, a firm is
required to give "at least seven days' notice" to suspend work if
it does not receive payment. CCS's chief executive said that he had
seen a number of cases where the notice period had been extended to
14 or 21 days. "Main contractors are exploiting the weak drafting
of the Act to extend the 'at least seven days' to a period much
longer than intended."
He has also noted clauses drafted in a way that are designed to
lengthen the period before an aggrieved party can apply for
adjudication if a dispute arises. Huxtable said that the common way
was to refer to the issue as not being a dispute but a "cause for
dissatisfaction." A period would then be specified for discussing
the "dissatisfaction" and only if this fails "will it be deemed to
be a dispute."
Huxtable said: "This introduces at least one month's delay before a
specialist can seek adjudication. This is particularly difficult
for specialists to argue against as the clauses are worded in a way
that seem conciliatory and in the spirit of Latham. But all it is
doing is further delaying payment."
Huxtable said: "We seem to be going back to the sad old days when
specialists only knew what they were being paid when they actually
got the money."
Once the CCS has fully analysed all the main contractors'
subcontracts, it will be sending its findings to construction
minister Nick Raynsford. Last week Raynsford said he would consider
tightening the Act if it was not working (see page 32).