The growing use of project managers in the construction industry in
recent years appears to be giving rise to an increased incidence of
litigation concerning the standards of care to be provided by
project managers.
The case of Pozzolanic Lytag Limited-v-Bryan Hobson Associates
gives an example of the type of duty owed by a project manager to
its client, the breach of which may create a right to recover
damages.
Pozzolanic is a company which buys pulverised fuel ash (PFA) from
power stations for sale to the construction industry for use in
concrete. It was negotiating with Powergen for the purchase of PFA
from a power station known as "Fiddlers Ferry."
In order to secure this contract, Pozzolanic needed to have
designed and constructed handling and storage facilities on the
site of the power station. Accordingly, it entered into an
agreement with Hobson Associates to carry out design and project
management services in relation to the works.
The works included the construction of a dome or spherical silo for
the storage of PFA, and the necessary groundworks. A main contract
was entered into with a company called HP Domes on the basis of JCT
1980 Standard Form of Contract with a contractor's design portion
supplement applicable to the dome.
specialist
It was a part of the contract that HP Domes would engage a
specialist design sub-consultant to check the structural design of
the dome. Hobson Associates remained responsible for the design of
the rest of the works.
Within a short period after completion the dome collapsed causing
losses to Pozzolanic in excess of £600,000. It was accepted
that the collapse was caused by defects in design which would
ordinarily be covered by professional indemnity insurance of the
type required to be provided under clause 21A of the JCT Standard
Form.
This clause provides "without prejudice to his liability to
indemnify the employer under clause 2.6 the contractor shall
maintain and shall cause any sub-contractor to maintain such
insurances as are necessary to cover the liability of the
contractor or, as the case may be, of such sub-contractor in
respect of his obligations under clause 2.6.
The amended clause 2.6 provided "the parts of the works comprising
the contractor's designed portion shall be fit for the purpose for
which they are required."
Reviewing its options Pozzolanic discovered that matters were not
as clear as it would have wished. The main contractor, HP Domes,
was worthless. Worse, this company had failed to put in place the
relevant design insurances.
The sub-consultant design checker did have in place a relevant
professional indemnity insurance, but no direct warranty had been
placed between this company and Pozzolanic. In the absence of a
contractual link to the sub-consultant, any action by Pozzolanic in
negligence would simply be 'speculative' litigation.
Accordingly Pozzolanic turned its attentions to its project
manager. The background to the matter of project insurances was
extremely confused.
To its credit, Hobson Associates had recommended the use of a
designed portion supplement for the dome and had drawn to the
attention of the main contractor the requirement for relevant
project insurances including insurances in respect of the
liabilities under clause 2.6.
Undoing this sound advice, Hobson had however written to the main
contractor suggesting that the sub-consultant would carry the
relevant professional indemnity insurance. Hobson had failed to
question whether or not the main contractor would benefit from such
a policy of insurance held in the name of the sub-consultant, or
whether the sub-consultant should be required to enter into a
collateral warranty.
Evidence
The main contractor replied by sending evidence of its own project
all risks insurance cover, which did not embrace design liability,
together with copies of its sub-consultant's design liability
policies. Hobson Associates had failed to comment upon the
inadequacy of these documents.
His Honour Mr Justice Dyson QC had to decide whether Hobson
Associates owed a duty to Pozzolanic to take reasonable care to
ensure there was in place insurances, as required by the contract,
which would cover the main contractor's liability in respect of
design obligations.
The terms of engagement of Hobson Associates made no express
mention of such a duty even though today it would be commonplace to
expect such a clause in a contract for project management services.
Expert evidence was called by both parties directed to the question
of whether an engineer appointed to undertake contract and project
management services had a duty to ensure that all insurances
required of the contractor by the contract documents were in place.
Text books and codes of practice referring to the role of the
project manager were cited but neither expert could agree.
conclusion
Nevertheless Judge Dyson concluded that a project manager did
indeed owe a duty to its client to ensure the placing of relevant
contract insurances.
It was unimportant that Hobson Associates did not have the
expertise necessary to assess the adequacy of the proposed
insurances. It could have obtained expert advice in that regard.
Furthermore, whilst Judge Dyson could see that certain clients
might be contributorily negligent where, for example, they
possessed relevant insurance expertise, this did not apply in the
present case to Pozzolanic.