Construction contracts can be hopelessly difficult documents to
understand and interpret. It is an everyday occurrence on
construction projects that there will be an argument concerning
whether work is included within the contract scope of work or is to
be treated as a variation.
Such arguments will involve a detailed examination of the contract
terms and conditions, relevant specification clauses, descriptions
contained in schedules of work or bills of quantities, and the use
of provisional sums. Where bills of quantities are used arguments
concerning the standard method of measurement will also be brought
into play.
All these components were in issue in the recent case between
Demolition Services Limited and Castle Vale Housing Action Trust
Limited. Castle Vale engaged Demolition to demolish two residential
tower blocks. The work involved the stripping out of asbestos in
the form of lagging material and in the form of sheets made up as
insulation barriers.
During the demolition work asbestos-containing materials were also
discovered in the finishes to some ceilings, walls and floors. This
work involved the stripping and disposal of part of the textured
coating on all the ceilings throughout the blocks, on the walls of
all the communal areas and on the walls of some of the bathrooms
and toilets of the flats. The asbestos was mainly in the form of an
additive to paint used in one of the paint layers in the wall and
ceiling coatings. Thermoplastic floor tiles containing small
quantities of asbestos were also found on every floor and landing.
The discovery of these asbestos-containing materials led the
contract administrator to instruct Demolition to suspend all
dismantling work. Lengthy discussions with the Health and Safety
Executive followed and a revised method statement was finally
agreed, dealing with the dismantling and removal of all finishing
materials containing asbestos. The debuilding process which
Demolition was planning to use to dismantle the structure of each
block was suspended until this stripping out work had been
completed.
Demolition claimed an additional £300,000 in respect of both
the suspension and the works relating to removing the
asbestos-containing materials. Castle Vale, on the other hand,
argued that the work formed part of the asbestos removal work
provided for in the schedule of works and did not warrant any
additional payment.
His Honour Judge Thornton QC had to decide whether Demolition was
entitled to be paid additional amounts and, if so, how that payment
should be made.
The schedule of works contained two key provisions which required
the removal of asbestos-based materials present in the structure
being demolished, and also required the contractor to include for
the identification and disposal of any asbestos, toxic waste and
the like. A provisional sum of £5,000 for additional asbestos
removal described as defined work was also included. Castle Vale
relied on the literal meaning of the relevant contract provisions
as showing that all asbestos was to be removed as part of the work
involved in the lump sum item for asbestos removal. They argued
that the provisional sum item was, in its contractual context, an
obvious mistake and should be ignored.
Judge Thornton considered that business commonsense should play an
important part in his interpretation of these provisions. He
referred to the case of Miramar Maritime Corporation -v- Holborn
Oil Trading Limited: "There must be ascribed to the words a meaning
that would made good commercial sense if the schedule of works were
issued in any of these situations, and not some meaning that
imposed upon a contractor a financial liability of unknown extent
that no businessman in his senses would be willing to incur."
The case of Wickman Tools -v- Schuler AG was also quoted: "The fact
that a particular construction leads to a very unreasonable result
must be a relevant consideration. The more unreasonable the result
the more unlikely it is that the parties can have intended it, and
if they do intend it the more necessary it is that they shall make
their intention abundantly clear."
Bearing these considerations in mind, Judge Thornton was satisfied
that the contract limited the asbestos disposal in question to
asbestos in the form of sheets or lagging. The additional asbestos
found in the wall, floor and ceiling finishes was not included in
that description. Furthermore it followed from the standard method
of measurement that where the available information did not enable
the work to be fully described and accurately quantified, detailed
provisions for the creation of provisional sums for such work must
be set out.
The asbestos removal referred to in the provisional sum, which was
stated to be defined work, was to be regarded as a reference to
asbestos removal of a kind and quantity which enabled the work to
be planned and programmed, such that preliminaries could be priced
in advance of demolition work. This could not be done in respect of
asbestos of the kind now in question, and accordingly the
additional payment fell to be valued in accordance with instructed
variations under the terms of the contract.